FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
5 Check Before Power-On
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
24
5
Check Before Power-On
Preparations
Tools: multimeter, screwdriver, step ladder, insulation megohmmeter, pressure gauge
Document: initial configuration parameter manual
Skill requirement: power distribution engineer
Check Before Power-On
Table 5-1
Items to be checked before power-on
System
Check Item
Operation Method
Reference
Integrated
cabling
Connecting
cables
Check cable
connections.
Check the cable
layout.
Check the cable
labels.
Cables are neat, tidy
not coiled, and
excessive parts are
cut.
Power cables are at
least 20 mm away
from signal cables.
Power cables are
bound at intervals of
at most 200 mm. For
thicker cables, the
intervals can be
greater.
Cable ties do not
overlap, and the joints
are evenly cut without
burrs.
Cables are placed
properly and not tense
at turning points.
Cable routes are
straight and smooth,
and do not intersect
inside a cabinet.