FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
6 Power-On Commissioning
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
29
Table 6-1
Checking after power-on
System
Check Item
Check
Sub-item
Criteria
Power supply
and distribution
system
Integrated UPS
MDU
The screen is free from erratic
display or missing characters.
Settings meet the requirements
of the current scenario.
The mains and bypass input
and output voltage, power,
frequency, current, power
factor, electricity energy, and
switch status are properly
displayed.
There is no active alarm whose
severity is higher than minor.
If there are any alarms, record
and handle the alarms.
Cooling system
Air cooled
precision smart
cooling product
Remote
temperature and
humidity (T/H)
sensor
The DIP switch settings are
the same as the initial settings.
Controller
The screen is free from erratic
display or missing characters,
and displays no alarm.
The teamwork settings are the
same as the initial settings.
Management
system
Monitoring
device
Camera
The red indicator inside the
camera is on.
ECC800
collector
The power indicator on the
main control board is on.
The indicator on the power
module is green.
Smart ETH
gateway
The PWR and RUN indicators are
on.
AC actuator
The PWR, RUN, and RF_Z
indicators are on.
WiFi converter
The RUN and WiFi indicators are
on, and the WPS indicator is off.
Access control
system
Pre-fab. module
door
The magnetic lock indicator is
green when the pre-fab.
module door is closed.
The magnetic lock indicator is
red when the pre-fab. module
door is open.
The pre-fab. module door can