FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
7 System Commissioning
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
36
Verify that all devices in the initial configuration table communicate with the management
system properly.
3.
Check that the views in the management system are consistent with the running status of
the data center. If any inconsistency is found, contact Huawei technical support.
Step 2
Commission the NetEco management system.
1.
Enter the initial user name and password on the NetEco WebUI to log in to the
management system.
2.
Check the connections of all monitoring devices by referring to the monitoring device
layout diagram.
Verify that all devices in the initial configuration table communicate with the management
system properly.
3.
Check that the views and videos in the management system are consistent with the
running status of the data center. If any inconsistency is found, contact Huawei technical
support.
----End
7.4 Commissioning the Fire Extinguishing System
(Standard)
Prerequisites
The fire alarm control panel has been powered on.
The management system is working properly.
Before commissioning the fire extinguishing system, disconnect all control cables to fire
cylinder electromagnetic valves to avoid extinguishant release and damage to equipment
due to misoperations during the commissioning. After the commissioning is completed,
reconnect cables to the electromagnetic valves.
Do not remove the safety pin before the fire extinguishing system is commissioned;
otherwise, extinguishant may be released due to misoperations.
To avoid damaging the detector probe, keep a proper distance between the heating device
and the heat detector probe.
Preparations
Tools: multimeter, smoke pistol, heating device, Phillips screwdriver, flat-head screwdriver