On-Off Test
This page will allow the user to force the carrier signal to either “On” or “Off.” This can be
useful in troubleshooting, tuning auxiliary coupling equipment or measuring levels etc. Forcing
the carrier will cause the PLC module to go into minor alarm. This reminds the user that the PLC
is not in its “normal” state.
Note:
Remember to always put the carrier back into the normal state before leaving the unit.
Menu location: Test > PLC
1
3
2
4
5
6 7
8
Figure 5-15. On/Off Test
1.
Force TX Carrier State:
Forces the carrier to one of three states as follows: Normal
Operation, Force On or Force Off.
2.
Activate:
Click to activate a change in the carrier state. The following confirmation
window will display. Click “Send Command,” an additional confirmation window will
briefly display to indicate either success or failure of the change in state.