GENERAL INFORMATION:
All 12” (304.8 mm) minimum supply wire outside of conduit.
Fixture mounting hook loop threads are 3/4‐14 NPS.
HOOK/LOOP MOUNTING: (Figures 5A, 5B & 5C)
Cord & Hook/Loop ordered as CxHLPx (Plug optional)
1.
If not already done, assemble the hook loop pieces according to the following steps.
2.
Thread the upper locknut (with flat surface down) onto the hook loop to approximately 1/8”
from the top of the threads. (Figure 5A)
3.
Position the safety clasp as shown and just start the fastener, but leave loose. (Figure 5A)
4.
Insert the power cord, must be rated minimum 90°C 16/3 SEOW‐A or equivalent, through the
hole in the hook and insert gotcha ring, top washer, gasket, lower washer and cast
bushing/nut onto cord. Fully tighten cast bushing against bottom of hook. (Figure 5A)
5.
Slide the assembly into the slot on the fixture yoke, so that the upper locknut is on top and
the tightened cast bushing is on the bottom and hand tighten the upper locknut. (Figure 5B)
6.
After the wiring is connected on the inside of the fixture, close the housing door such that
the tab on the cover fits under the top exposed locknut on the hook loop. (Figure 5C)
7.
Once fixture is fastened closed, tighten the upper locknut with a pair of pliers.
CAUTION: DO NOT TIGHTEN THE HOOK BY USING A SCREWDRIVER BLADE ‐ TOO MUCH
FORCE COULD BREAK THE HOOK. (Figure 5C)
HOOK
LOOP
UPPER
LOCKNUT
WASHER
SAFETY
CLASP
FASTENER
SAFETY
CLASP
FIGURE 5C
HOOK LOOP ASSEMBLY
GOTCHA
RING
OPTIONAL
PLUG SHOWN
GASKET
WASHER
CAST NUT
UTB2
INSTALLATION INSTRUCTIONS
Hubbell Lighting, Inc. Doc. No. 93097040
A subsidiary of Hubbell Incorporated Revision P0
701 Millennium Drive • Greenville, SC 29607 Page 5 Phone (864) 678-1000
FIGURE 5A
HOOK LOOP ASSEMBLY
FIGURE 5B
HOOK LOOP ASSEMBLY
GENERAL INFORMATION:
All 12” (304.8 mm) minimum supply wire outside of conduit.
Fixture mounting hook loop threads are 3/4‐14 NPS.
HOOK/LOOP MOUNTING: (Figures 5A, 5B & 5C)
Cord & Hook/Loop ordered as CxHLPx (Plug optional)
1.
If not already done, assemble the hook loop pieces according to the following steps.
2.
Thread the upper locknut (with flat surface down) onto the hook loop to approximately 1/8”
from the top of the threads. (Figure 5A)
3.
Position the safety clasp as shown and just start the fastener, but leave loose. (Figure 5A)
4.
Insert the power cord, must be rated minimum 90°C 16/3 SEOW‐A or equivalent, through the
hole in the hook and insert gotcha ring, top washer, gasket, lower washer and cast
bushing/nut onto cord. Fully tighten cast bushing against bottom of hook. (Figure 5A)
5.
Slide the assembly into the slot on the fixture yoke, so that the upper locknut is on top and
the tightened cast bushing is on the bottom and hand tighten the upper locknut. (Figure 5B)
6.
After the wiring is connected on the inside of the fixture, close the housing door such that
the tab on the cover fits under the top exposed locknut on the hook loop. (Figure 5C)
7.
Once fixture is fastened closed, tighten the upper locknut with a pair of pliers.
CAUTION: DO NOT TIGHTEN THE HOOK BY USING A SCREWDRIVER BLADE ‐ TOO MUCH
FORCE COULD BREAK THE HOOK. (Figure 5C)
HOOK
LOOP
UPPER
LOCKNUT
WASHER
SAFETY
CLASP
FASTENER
SAFETY
CLASP
FIGURE 5C
HOOK LOOP ASSEMBLY
GOTCHA
RING
OPTIONAL
PLUG SHOWN
GASKET
WASHER
CAST NUT
UTB2
INSTALLATION INSTRUCTIONS
Hubbell Lighting, Inc. Doc. No. 93097040
A subsidiary of Hubbell Incorporated Revision P0
701 Millennium Drive • Greenville, SC 29607 Page 5 Phone (864) 678-1000
FIGURE 5A
HOOK LOOP ASSEMBLY
FIGURE 5B
HOOK LOOP ASSEMBLY
GENERAL INFORMATION:
All 12” (304.8 mm) minimum supply wire outside of conduit.
Fixture mounting hook loop threads are 3/4‐14 NPS.
HOOK/LOOP MOUNTING: (Figures 5A, 5B & 5C)
Cord & Hook/Loop ordered as CxHLPx (Plug optional)
1.
If not already done, assemble the hook loop pieces according to the following steps.
2.
Thread the upper locknut (with flat surface down) onto the hook loop to approximately 1/8”
from the top of the threads. (Figure 5A)
3.
Position the safety clasp as shown and just start the fastener, but leave loose. (Figure 5A)
4.
Insert the power cord, must be rated minimum 90°C 16/3 SEOW‐A or equivalent, through the
hole in the hook and insert gotcha ring, top washer, gasket, lower washer and cast
bushing/nut onto cord. Fully tighten cast bushing against bottom of hook. (Figure 5A)
5.
Slide the assembly into the slot on the fixture yoke, so that the upper locknut is on top and
the tightened cast bushing is on the bottom and hand tighten the upper locknut. (Figure 5B)
6.
After the wiring is connected on the inside of the fixture, close the housing door such that
the tab on the cover fits under the top exposed locknut on the hook loop. (Figure 5C)
7.
Once fixture is fastened closed, tighten the upper locknut with a pair of pliers.
CAUTION: DO NOT TIGHTEN THE HOOK BY USING A SCREWDRIVER BLADE ‐ TOO MUCH
FORCE COULD BREAK THE HOOK. (Figure 5C)
HOOK
LOOP
UPPER
LOCKNUT
WASHER
SAFETY
CLASP
FASTENER
SAFETY
CLASP
FIGURE 5C
HOOK LOOP ASSEMBLY
GOTCHA
RING
OPTIONAL
PLUG SHOWN
GASKET
WASHER
CAST NUT
6. After the wiring is connected on the inside of the fixture, close
the housing door such that the tab on the cover fits under the top
exposed locknut on the hook loop. (Figure 5C)
7. Once fixture is fastened closed, tighten the upper locknut with a
pair of pliers.
CAUTION: DO NOT TIGHTEN THE HOOK BY USING A SCREWDRIVER
BLADE; TOO MUCH FORCE COULD BREAK THE HOOK. (Figure 5C)
UTB2
INSTALLATION INSTRUCTIONS
Hubbell Lighting, Inc. Doc. No. 93097040
A subsidiary of Hubbell Incorporated Revision P0
701 Millennium Drive • Greenville, SC 29607 Page 5 Phone (864) 678-1000
FIGURE 5A
HOOK LOOP ASSEMBLY
FIGURE 5B
HOOK LOOP ASSEMBLY
GENERAL INFORMATION:
All 12” (304.8 mm) minimum supply wire outside of conduit.
Fixture mounting hook loop threads are 3/4‐14 NPS.
HOOK/LOOP MOUNTING: (Figures 5A, 5B & 5C)
Cord & Hook/Loop ordered as CxHLPx (Plug optional)
1.
If not already done, assemble the hook loop pieces according to the following steps.
2.
Thread the upper locknut (with flat surface down) onto the hook loop to approximately 1/8”
from the top of the threads. (Figure 5A)
3.
Position the safety clasp as shown and just start the fastener, but leave loose. (Figure 5A)
4.
Insert the power cord, must be rated minimum 90°C 16/3 SEOW‐A or equivalent, through the
hole in the hook and insert gotcha ring, top washer, gasket, lower washer and cast
bushing/nut onto cord. Fully tighten cast bushing against bottom of hook. (Figure 5A)
5.
Slide the assembly into the slot on the fixture yoke, so that the upper locknut is on top and
the tightened cast bushing is on the bottom and hand tighten the upper locknut. (Figure 5B)
6.
After the wiring is connected on the inside of the fixture, close the housing door such that
the tab on the cover fits under the top exposed locknut on the hook loop. (Figure 5C)
7.
Once fixture is fastened closed, tighten the upper locknut with a pair of pliers.
CAUTION: DO NOT TIGHTEN THE HOOK BY USING A SCREWDRIVER BLADE ‐ TOO MUCH
FORCE COULD BREAK THE HOOK. (Figure 5C)
HOOK
LOOP
UPPER
LOCKNUT
WASHER
SAFETY
CLASP
FASTENER
SAFETY
CLASP
FIGURE 5C
HOOK LOOP ASSEMBLY
GOTCHA
RING
OPTIONAL
PLUG SHOWN
GASKET
WASHER
CAST NUT
OPTICS WIRE GUARD INSTALLATION (If Optioned):
1. With mounting screws removed from heatsink, install full wire guard (WG-16) onto Reflector.
2. Install Reflector onto fixture heatsink using screws (4x) provided.