3-2
D
RIP
P
IPING AND SPLASHGUARDS
INSTALLING SPLASHGUARDS
After merchandisers have been leveled and joined,
and all drip piping, electrical and refrigeration
work has been completed, install the splashguards.
1. Check to be sure that all lower body panels
are level with the floor. Tighten screws.
2. Apply double-stick tape to back of splashguard
along the top.
3. Position all the splashguard sections before
removing backing paper from tape.
4. Once all sections are positioned, remove bak-
ing paper from one section and press it firmly
against the body panel.
5. Continue, section by section, until all are
installed.
SEALING SPLASHGUARD TO FLOOR
I
F REQUIRED
by local sanitation codes, or if
desired by the customer, splashguards may be
sealed to the floor using a vinyl cove base trim.
The size of trim needed will depend on how
much the floor is out of level.
To install the trim to the splashguard:
1. Remove all dirt, wax and grease from the area
of the splashguard where adhesion will be
necessary. This is to ensure a good and secure
installation.
2. Apply a good contact cement to the cove trim
and allow proper drying time according to the
directions supplied with the cement.
3. Install the trim to the splashguard so that it is
lying flush with the floor. D
O NOT SEAL THE
TRIM TO THE FLOOR
.
4.
If required by local health codes
the Cove
Trim may be sealed to the floor, using a sili-
cone type sealer. Sealant must be removed
and replaced when servicing.
P/N 0446551_A
WWW
.
HUSSMANN
.
COM
Splashguard
Cove Trim
Cement
Body Panel