21
Installation
1. Installation method
This welding machine use 50A electric leak protection switch, fuse capacity 40A.
Make sure the distribution switch is off before install the machine. Don’t install
the machine when hand is wet, don't put items on the welding cable, follow the
steps below:
Connect the machine input cable stably with the electric socket. The required
input voltage must be AC220Vm input cable must be ≥6mm
2
. The yellow and
green cable must be connect stably with the lead cable.
Connect the welding cable and lead cable into the plug, turn clockwise until
fixed well.
All the welding copper cable should be ≥16mm
2
.
When the welding cable length more than 20m, the square meter of the cable
should enlarge.
Installation and Operation
Summary of Contents for ZX7-200
Page 1: ......
Page 2: ......
Page 12: ...8 2 安装示意图 五 安装及操作 ...
Page 15: ...11 1 焊机 壹台 2 电缆插头 两个 3 使用说明书 产品合格证 保修条例 各壹份 七 产品装箱单 ...
Page 16: ...12 八 电气原理图 ...
Page 29: ...25 Electric Diagram ...
Page 31: ......
Page 32: ......