background image

Beta Match

() Select the Beta Match tubes (3/4" x 17"), the beta support insulator and clamp as
shown in Figures 3 and 6. Make certain the drilled ends of the beta tubes are pointed
towards the Driven Element.

( ) Select the Beta Match shorting strap and the shorting clamp and assemble as
shown in Figure 6. Notice that the 10-24 x 1

 

1/2" 

screw attaching the shorting straps to

the clamp has a sleeve slipped over it. This allows you to install the shorting straps
without causing undue strain on the Beta Match tube.

( ) Install the pigtail assembly (wire with solder lug on each end) on the Beta Match
tubes using the two #10 metal screws and lockwashers. Slip the 1 ¼”

 

tubing clamps

on the driven element near the insulators. Loosely attach the pigtails to the tubing
clamps using the ¼”-20 x 1 ½” screws as shown in Figure 6. Do not tighten the
connection at this time. The coaxial feedline will connect to this point in a later step.

Director Element

( ) Select the remaining set of element-to-boom brackets and loosely assemble on the

Assembly

boom 80

 

3/8" from the center of the driven element-to-boom bracket to the center of  the

                                             Director Element-to-boom bracket. Refer to Figure 3 and 4. Do not forget the anchor screws
                                             as shown in Figure 4.

( ) Select the D-1 section of tubing (1'/." x 28"). Insert the D-1 section into the bracket
assembled on the boom. Tighten the screws to hold the element securely but do 

not

tighten the anchor screws at this time.

Summary of Contents for DB-1015A

Page 1: ... 10 and 15 Meter Duo Band Antenna Order No HY GAIN ELECTRONICS CORPORATION 8601 Northeast Highway 6 Lincoln Nebraska 68505 Telephone 464 9151 Area Code 402 printed copyright Hy Gain Electronics Corporation At rights ...

Page 2: ...al 1 Specifications 1 Theory of Operation 1 SECTION II ASSEMBLY AND INSTALLATION Preparation of Assembly 2 Boom Assembly 2 Reflector Element Assembly 3 Driven Element Assembly 5 Befa Match 6 Director Element Assembly 6 Final Assembly 8 SECTION III PARTS LIST 8 ...

Page 3: ...5 8 O D Wind surface area 3 8 sq ft Wind load 80 mph 97 3 lbs Theory of Operation Hy Gain Hy Q traps are air dielectric parallel resonant circuits which operate as electronic switches On 10 meters the switch is open so only the inner portions of the e ements are operative giving a three element 10 meter beam On 15 meters the switch is closed and the entire element is operative giving a three eleme...

Page 4: ... dimensions given in this manual for optimum results from your antenna Boom Assembly Select the two boom sections 2 diameter tubing and the boom to mast brackets Loosely assemble the boom to mast bracket using the 20 x screws nuts and lockwashers as shown in Figure 2 Slip the drilled end of each boom section into the boomto mast bracket and line up the holes Attach the boom to the bracket using th...

Page 5: ...ely but do not tighten the anchor screw at this time Check to see that the Reflector element will lie in a plane horizontal to the earth when the antenna is mounted on your mast Do this by observing the position of the element with respect to the boom to mast bracket Make any adjustments necessary keeping the center of the bracket 3 from the tip of the boom then tighten the anchor screws securely ...

Page 6: ...ce To decide which transmiting mode is best for your purposes refer to the VSWR charts in Figure 7 Assemble a 1 compression clamp and slip it onto the unswaged end of the R 2 section Select the 10 meter trap and slip the unswaged end into the R 2 section Measure the dimension shown on Figure 3 for your mode of transmission Make certain the trap drain holes are facing downward Tighten the compressi...

Page 7: ...ession clamp and slip it over the DE 1 section Select the DE 2 section 1 1 8 x 52 Slip the unswaged end of the DE 2 section into the DE 1 section and measure the dimension shown on Figure 3 for your mode of transmission Tighten the compression clamp slightly Assemble a 1 compression clamp and slip it over the swaged end of the DE 2 section Select a 10 meter trap and slip the unswaged end into the ...

Page 8: ...10 metal screws and lockwashers Slip the 1 tubing clamps on the driven element near the insulators Loosely attach the pigtails to the tubing clamps using the 20 x 1 screws as shown in Figure 6 Do not tighten the connection at this time The coaxial feedline will connect to this point in a later step Director Element Select the remaining set of element to boom brackets and loosely assemble on the As...

Page 9: ...compression clamp and slip it over the swaged end of D 2 Select a 10 meter trap and slip the unswaged end into the D 2 Measure the dimension shown in Figure 3 for your mode of transmission Make certain the trap drain holes are facing downward and tighten the compression clamp slightly Assemble a 11 16 compression clamp and slip it over the swaged end of the 10 meter trap Select the D 3 section 7 1...

Page 10: ...in balun Model BN 86 available at your local Hy Gain dealer The BN 86 allows the DB 1015A to operate with an efficiency greater than is possible with a homemade choke Your DB 1015A is now ready to be installed on a 1 5 8 O D mast Use one of the methods explained at the beginning of this section When mounting the completed antenna be certain to pin the bracket to the mast as explained in the sectio...

Page 11: ...or improperly installed or used The warranties contained herein are the sole express warranties made by Hy Gam Electronics Corporation on this product _ LIMITATION OF DURATION OF IMPLIED WARRANTIES IMPLIED WARRANTIES INCLUDING WITHOUT LIMITATION WARRANTIES OF MERCHANTABILITY OR FITNESS ARE EXPRESSLY LIMITED IN DURATION TO THE 90 DAY PERIOD OF THIS WARRANTY Some states do not allow limitation on no...

Reviews: