Starting up the unit
Starting up the unit
Before the unit is put into operation, it must first be connected hydraulically
and electrically, as described in the above chapters.
Note that the OLSW unit contains no filter or coalescing elements when it
leaves the factory. If necessary, install the elements.
Proceed as follows for commissioning:
1. Close the ball valve at the "INLET WATER"
and OUTLET WATER.
2. Close the ball valve "Drain"
3. Prefill the motor pump group to the top with
operating medium using the filling supports.
Open the ball valve INLET WATER.
4. Switch on the unit at the main switch.
5. The filter housing and the coalescing
housing will be filled and automatically
vented.
6. Check the flow at the flow indicator.
7. If no air exits at the breather, then the filter
and coalescing housing is full.
Open the ball valve OUTLET WATER.
8. The unit is ready for operation.
OLSW
en(us)
Page 37 / 76
BeWa OLSW 4268435 en-us 2017-11-09.docx
2017-11-09
Summary of Contents for OLSW