8. Commissioning
Risk of operating error!
Start-up of the unit is restricted to expert staff
only (electricians or expert personnel with
equivalent training).
Step 1: Check of mechanical integrity and
wiring
»
Open housing cover.
»
Check cylinder seating.
»
Check steam, condensate and
drainhose clamps.
»
Check that all electrical wire connec-
tions (including steam cylinder wir-
ing) are tight and secure.
Step 2: Switching on the steam humidifier
»
Switch on main breaker.
»
Open water supply stopcock (opera-
ting pressure should be 1bar min.,
10bar max./14.5 psi min., 145 psi
max.).
»
Switch on unit by setting control
switch to “I”.
Step 3:
The unit performs a self-test and,
then, commences normal operation
•
During self-test, the On/Off button icon
flashes for a couple of seconds
•
On completion of the test, the software
version is displayed for a short
moment. Consequently, normal opera-
tion is commenced. However, steam is
not produced without a demand pen-
ding
Step 4: Trigger steam demand
»
Set control for commissioning check
for permanent steam demand and
close safety interlock.
The water inlet solenoid valve opens and
feeds water into the steam cylinder
Step 5: Monitor unit function and check
for leakage
»
Let unit operate for 15 to 30 minutes.
»
If leaks appear, switch off the unit.
Risk of electrical shock!
Hazardous electrical voltage!
Follow safety instructions for work on live
components.
Step 6: Repair leaks
»
Find leaks and eliminate.
»
Check again for leaks.
»
When everything is o.k., reattach
housing cover.
WARNING
!
WARNING
!
Summary of Contents for FlexLine FLH03
Page 1: ...FlexLine Electric Heater Steam Humidifiers ÁFLH ENKÈ FLH EN E 8881164 Manual ...
Page 45: ...Page 45 11 Declaration of Conformity ...
Page 49: ...Page 49 This page intentionally left blank ...
Page 50: ...Page 50 This page intentionally left blank ...