- 3 -
Connection of Water Part
The HY-
MAG
Water Conditioning Units are supplied ex works in 2 components, that means
water part and control box.
Connection between control box and water part must be provided by expert plumbers as
follows:
HY-
MAG
DN25
– DN65
The control box includes a mains connection cable and a load cable for the connection of the
water part. Such load cable is provided with a Harting plug. To guarantee a correct
connection of the water part, it is necessary to insert the Harting plug into the Harting
bushing on the water part and to fix it by the safety bracket. A code bar on the plug / bushing
guarantees a correct connection.
It is only possible and allowed to start or put the control box in operation if the Harting plug
between control box and water part has been closed!
The connection cable between control box and water part is a spiral cable. Max. distance
between both unit components shall not exceed 1.5 m!
HY-
MAG
DN100
The control box for the HY-
MAG
DN100 does include a mains connection cable, a load cable
and a cable to connect the thermal protection.
The connection box (terminal strip) provided on the water part is necessary to make the
appropriate connection at plant installation:
Connection coil:
load cable
Connection thermal
protection:
thermal protection cable
To guarantee a correct connection of the water part, it is necessary to fix the corresponding
cable ends in the specific and marked terminals.
It is only possible and allowed to start or put the control box in operation if the connection is
properly made correctly and the terminal or connection box closed!
The connection cable between control box and water part is a spiral cable. Max. distance
between both unit components shall not exceed 1.5 m!