HYLITE MIGHTYLITE PRO – INSTALLATION AND OPERATING INSTRUCTIONS

The Hylite Mightylite Pro floodlight a high-powered, professional LED floodlight which is suitable for use outdoors in a range of 

commercial applications including lighting perimeters, car parks, garden areas and outside warehouse facilities.

The unit requires connection to a 230 AC 50Hz mains electricity supply.

1. IMPORTANT SAFETY INSTRUCTIONS

WARNING: THIS PRODUCT MUST BE INSTALLED BY A QUALIFIED ELECTRICIAN, AND CHECKED TO ENSURE 
IT IS SAFE, BEFORE USING.

PLEASE FOLLOW THESE INSTRUCTIONS CAREFULLY BEFORE ATTEMPTING TO INSTALL AND OPERATE 
THIS LIGHT.

1.1. IMPORTANT INSTALLATION INSTRUCTIONS

  

The risk of electric shock should be minimized by the installation of appropriate safety devices including the incorporation 

  of an RCCB (Residual Current Circuit Breaker) into the main distribution board.

    DO NOT wire this floodlight into the lighting circuit. Use a switched fused spur. Cables should always be protected against 

  short circuit and overload by use of an RCD.

    Ensure the voltage marked on the product is the same as the electrical power supply to be used.

    DO NOT install the light indoor or where it is likely to be knocked or hit; in hot or humid conditions such as near an exhaust 

  outlet e.g. boiler flue, dryer outlet.

1.2. IMPORTANT OPERATION & MAINTENANCE INSTRUCTIONS

  DO NOT position the light near flammable or combustible materials (such as wood, cloth, paper) or near flammable,  

 

  combustible or explosive liquids, solids, gases or equipment.

  DO NOT direct the light into a person’s eyes. This light has a very intensive light output, which if incorrectly used could 

  cause eye damage.

  ALWAYS disconnect the mains power supply before servicing or performing any maintenance.

  

  ALWAYS maintain the light in good condition, with repairs only undertaken by a qualified electrician.

  ONLY carry out repairs using genuine parts. Non-authorized parts may be dangerous and will invalidate the warranty.

1.3. PARTS INCLUDED 

1x Mightylite Pro LED Floodlight with connection 

  box and cable gland
1 x Allen key
2 x Allen Screws M3 X 10 HE
2 x M8 X 12 Bolts
2 x M8 X 12 Large washer
6 x M8 x 10 Spring Washer
2 x M3 Small Washer
4 x Plastic Screw Cover 6mm
4 x Pipe Bracket Screw and Nut Stainless Steel 1/4 x 
3/4
1 x Pipe Bracket 35.5cm Long
1 x U-Bracket 125mm x 320mm x 125mm

1.4. TOOLS REQUIRED

Electric/hand-held drill
No.8 masonry drill bit
Electricians screwdriver
Large cross-head screwdriver
Small cross-head screwdriver
Wire cutters

THIS PRODUCT IS SUITABLE FOR WALL 
MOUNTING ONLY

Summary of Contents for MIGHTYLITE PRO MLP120

Page 1: ...Installation operating instructions Mightylite Pro 120W 200W LED Floodlights Models MLP120 MLP200 ...

Page 2: ...t is likely to be knocked or hit in hot or humid conditions such as near an exhaust outlet e g boiler flue dryer outlet 1 2 IMPORTANT OPERATION MAINTENANCE INSTRUCTIONS DO NOT position the light near flammable or combustible materials such as wood cloth paper or near flammable combustible or explosive liquids solids gases or equipment DO NOT direct the light into a person s eyes This light has a v...

Page 3: ...ch the Mightylite Pro to the U bracket using the two securing bolts provided Fig 2 Position the unit against the mounting surface and mark the position for the U bracket ensuring the wires can easily reach the unit Use the U bracket Fixing Holes Fig 3 to mark the 4 drill holes required to secure the U bracket to the wall and mark the cable outlet location if required Detach the Mightylite Pro from...

Page 4: ...OWER SUPPLY IMPORTANT The Mightylite Pro has two dual channel drivers which control the 4 LED arrays within the Mightylite Pro The four BROWN Live wires in the Mightylite Pro terminal each operate as the Live for each of the LED arrays enabling the arrays to be wired to be switched on and off independently of each other See Section 4 2 Wiring Options The two BLUE Neutral wires in the terminal oper...

Page 5: ...en the 2 Securing bolts then use the 2 x Allen screws and washers to lock the position of the Mightylite Pro on the U bracket Fig 11 Fig 10 Fig 11 Fig 9 Wiring for Four Lighting Levels using 2 units Note A separate switch is used to control each of the four LED arrays within one or more Mightylite Pro units Diagram shows 2 units wired together so that both can operate at 25 50 75 or 100 light leve...

Page 6: ...lycarbonate Matt black aluminium Frosted 120W 80 280V 0 9 12000 96 LEDs 80 50 000 hrs Yes 220 H x 325 W x 125 D 3 years ANSI 5700K 40 C to 60 C Yes 5 0 MLP200B Mightylite PRO 200W Floodlight Matt black polycarbonate Matt black aluminium Frosted 200W 80 280V 0 9 17000 168 LEDs 80 50 000 hrs Yes 220 H x 325 W x 125 D 3 years ANSI 5700K 40 C to 60 C Yes 5 0 Tel 44 0 1352 736120 www f4enterprises co u...