1.3                       

·

 

Before installation, recommend preventing the module from exposure to direct sunlight or other light 

source. (If modules are exposed directly to sunlight without connection, each module generates over 

DC 30V, which is potentially hazardous.) 

·

 

Modules  are  heavy.  Be  sure  to have  more  than  two  persons  with anti-slip  gloves  on  carry  each  PV 

module. Do not throw and drop PV modules. 

·

 

Do not sit, stand, step, walk and/or jump on the module, including the frames. 

·

 

Do not drop or place objects on the modules. Do not place excessive loads on the modules or twist 

the module frame. 

·

 

All installation equipment and PV modules must be kept in dry condition during installation. 

·

 

Check  the  current  and  the  voltage  before  connecting  the  line.  There  is  potential  hazard  in  case  of 

higher voltage in series connection and higher current in parallel connection. 

·

 

All  PV  modules  must  be  earthed  by  using  earth  device.  Safety  check  for  all  other  parts  of  systems 

should be finished before installation to prevent any electric hazard. 

·

 

Do not use any damaged PV module, where it may cause fire, electric shock or injury. 

·

 

Do not focus light on a PV module, where it may cause fire and damage. 

·

 

Do  not  touch  live  parts  of  wires,  cables,  connectors,  or  junction  boxes,  in  order  to  prevent  electric 

shock 

and  injury.  Be  sure  the  circuit  breaker  is  off  if  it’s  applicable.  Always  use  appropriate  safety 

equipment. (Insulated tools, insulating gloves, etc.) 

·

 

Do not re-arrange bypass diodes, where it may cause electric shock and injury. 

·

 

Do not disconnect the cable when the load to module is engaged. 

·

 

Check applied Class for module after installing the module. 

·

 

Do not remove any labels.

 

1.4                          

·

 

In  order  to  prevent  any  performance  drop,  damage,  or  incapability,  do  not  use  paint  and  adhesive 

material to the module surface. 

·

 

Do not leave modules in places where flammable gases can be generated or collected. 

·

 

Do not leave un-fixed and unsafe PV modules unattended. 

·

 

Do not wear metallic rings, watchbands, ear, nose, lip rings or other metallic devices while installing 
photovoltaic systems.

   

·

 

Installers should be careful of 

module’s sharp parts(ex: the edges of module)

 

 

1.5   General Safety 

The following requirements should be kept during installation and inspection. 

·

 

Check the inspection requirements by authorized personnel. 

·

 

When installing the system, abide by all local, regional and national statutory regulations. 

·

 

System designer and installers should secure safe installation of PV modules. All installation must be 

conformed  to  all  fire  safety  regulations.  Additional  structures  can  be  applied  for  installation.  If 

additional  equipment  is  applied,  it  is  necessary  to  check  the  fuse  status,  earth  error  and  system 

isolation. 

·

 

Do not use different types of PV module in a same module array. 

·

 

Abide by the safety regulations for all other components within the total system. 

Summary of Contents for HiE-S SG Series

Page 1: ... Different regions may have different regulations for solar PV installations In this manual hereafter IEC only is used to refer to regions where IEC standard applies e g Europe Middle East most of Asia Pacific countries UL only is used to refer to regions where UL standard applies e g United States Canada all other references are global 1 1 Installing solar photovoltaic systems requires specialize...

Page 2: ... connectors or junction boxes in order to prevent electric shock and injury Be sure the circuit breaker is off if it s applicable Always use appropriate safety equipment Insulated tools insulating gloves etc Do not re arrange bypass diodes where it may cause electric shock and injury Do not disconnect the cable when the load to module is engaged Check applied Class for module after installing the ...

Page 3: ...s and modules which might cause module damage and cell crack during transportation Store the modules safely in a dry and cool environment Do not stack or move more than two packages of modules which are stacked vertically Workers are recommended to keep some distance from the package when one worker cuts banding tapes Don t lift the package after removing banding tapes After unpacking please visua...

Page 4: ...educe pressure loads and improve module ventilation The minimum distance between a module frame and a sidewall of clamp for linear thermal expansion of the module frame supports should be 1 5 mm in order to reduce pressure loads All the junctions on the conductive connection must be fixed Metal containing iron in the conductive connection should be made with stainless steel or be treated against c...

Page 5: ...lled in sulfurous area near sulfurous volcano and sulfurous spring If PV modules are installed near factory or plant area they can be polluted by fumes and the pollution may not be cleaned Thus the installer should consider and check the installation area and the distance from factory or plant area If PV modules are installed in damp environments the installer should check the installation area to...

Page 6: ...nam si Gyeonggi do 13591 Korea Factory 313 Soi ro Soi myeon Eumseong gun Chungcheongbuk do 369 872 Korea Module M8 Screw Flat washer Spring washer M8 Nut The Support rail Picture 1 Installation Method using stainless steel bolt nut The support rail Clamp B Clamp A Picture 2 Mounting Hardware Clamp ...

Page 7: ... a module arrangement with combined electrical connection The array must be insulated to resist against the possible maximum open circuit voltage Also solar irradiation proof copper wires must be used for array wiring Installers must check the local electrical specifications In order to prevent cable drooping installers should fix cable using wire or duct 5 4 Earth Ground Wiring To prevent electri...

Page 8: ...On the junction box the polarity is clearly marked 1 Protection Degree IP67 2 Temperature Range 40 C 90 C 3 Wire Size 4 0mm 2 AWG 12 4 The cable must not be bent or crushed on the direct exit of the cable screw joint A minimum bending radius 43mm must be maintained The cable must be routed in a way that tensile stress on the conductor or connections is prevented Picture 4 Picture 4 Cable Routing 5...

Page 9: ...modules are equipped with bypass diodes If installer wishes to change into other diodes the installer should inform an authorized engineer of HES Object Manufacturer Type Technical Data Junction Box Zhejiang Renhe Photovoltaic Technology Co Ltd GF26xy Max Voltage 1500 V DC Rated current 15 A RTI 110 Bypass diodes PST6020 Tj max 200 C If 20A PST4530 T Tj max 200 C If 20A Cable H1Z2Z2 K 1 x4 0 mm 2 ...

Page 10: ... module glass surface clean For AR coating HES modules utilize special materials to increase energy harvest Always use clean gloves when handling the module never touch the glass with bare hands If dirt build up becomes excessive clean the glass surface with room temperature water and soft materials without potential risks of scratch Do not use water with high pressure for cleaning Do not use hars...

Page 11: ...t have any responsibility and liability for clause as below Loss damage injury or expense resulting from improper installation handling or use The installation techniques handling and use of this product are beyond company control Infringement of any third party s patent or right that is caused by using HES modules Loss damage injury or expense resulting from any factor that is unsuspected the mod...

Page 12: ...d Safety factor 1 5 Method SG Overlap of Clamp with Al frame 8 10mm SI Overlap of Clamp with Al frame 9 11mm Bolting 4 Bolts 1600 1600 Pa 8 Bolts 3600 1600 Pa Clamping Clamping area Min Clamp Width 50mm on Long Bar A 330 50mm 3600 1600Pa or 2400 2400 Pa A 330 50mm Design load 2400 2400Pa A 330 50mm B 971 50mm Design load 3600 1600Pa Note 1 Certified by TUV NORD 2 The Mounting method has been quali...

Page 13: ...utput tolerance W 5 0 Maximum system voltage Vdc IEC 1 500 Cell quantity in series pcs 340 Bypass diodes pcs 2 Cell Type Mono crystalline Silicon Cell Application Safety Class Class A Class II Fire rating Class C IEC Electrical Characteristics HiE SxxxSI Item HiE SxxxSI xxx Maximum Power Value Maximum Power at STC Pmax W 420 415 410 405 400 395 Voltage at Pmax Vmpp V 37 7 37 6 37 5 37 4 37 3 37 2 ...

Reviews: