1-15
INSTALLATION
SL 20-115 MODULATING GAS BOILER
1.5.3 Condensate Trap
Assembly - cleaning
procedure
1.
turn off the power to the boiler
and allow it to cool down.
2.
remove the trap from the boiler
(reverse the installation procedure
above).
3.
remove the trap Cleanout
assembly (H), from the trap Body
and clean and flush the debris out.
4.
re-assemble trap components,
re-fill trap, and replace on boiler
as described in the installation
instructions above.
1.5.4 Further installation details
•
Condensate drain must be piped to within 1” of a drain or be connected to a
condensate pump.
•
drainage line must slope down to the drain at a pitch of 1/4” per foot so
condensate runs towards the drain.
•
Condensate traps should be checked every 2 months, and cleaned and
refilled as necessary.
NOTE
It is the responsibility of
the installing and/or service
Contractor to advise and
instruct the end User in how
to perform the Trap cleaning
procedure, and to advise
that the Trap be checked at
least every two months and
cleaned as required.