1-17
INSTALLATION
SL 20-115 MODULATING GAS BOILER
Figure 20: Overview of piping options
Water PiPing
1.6.1 General Piping Issues
the sl 20-115 boiler was designed to be easy to install in almost any application.
its unique multi-port piping design allows connection from either side or both
sides at once. With the purchase of the optional bottom connection kit, available
from iBC, piping can be routed below the unit for connection to system piping or
primary loop.
Primary/secondary piping, or the use of a hydraulic separator is recommended
for maximum flexibility in multi-load applications, but piping loads in parallel
is also encouraged in systems that only have two loads, or when loads are
operating simultaneously. the extremely low pressure drop through the sl series
heat exchanger allows many options not available in other designs. in short –
iBC has built a boiler that will allow you to pipe the system the way you prefer,
rather than try and dictate your piping practices from boiler to radiator.
there are some important details to consider however, and this section of the
installation and operating Manual will walk you through them so you can enjoy a
trouble-free installation.
1.6
Water outlet, right side
Outlet, left
Water inlet, right side
Inlet, left