3.
Fill the condensate trap with water, and
ensure that the bottom union cap is
hand-tightened to prevent leakage.
4.
Loosen the upper union nut, and slide
the trap over the boiler drain outlet, and
then tighten the upper union nut.
5.
To reinstall the condensate retainer, tilt
the retainer to enable you to slide the
two tabs under the chassis of the boiler,
and secure with the wing nuts.
6.
The drain hose should run to a suitable
drain or condensate neutralizer.
39
3.9 Installing the condensate trap
Summary of Contents for SL Series
Page 8: ...Intentionally left empty...
Page 12: ...Figure 5 Top view SL 40 399 G3 Figure 6 Bottom view SL 40 399 G3 8 Section Specifications...
Page 14: ...Intentionally left empty...
Page 64: ...Figure 40 Electric wiring connections 60 Section Installation...
Page 76: ...Intentionally left empty...
Page 96: ...Intentionally left empty...
Page 108: ...Intentionally left empty...
Page 110: ...Internal wiring diagram Figure 46 Internal wiring diagram 106 Section Appendices...
Page 111: ...Sequence of operations Figure 47 Sequence of Operation 107 Sequence of operations...