3.12 Gas piping
Note
Due to the precision of modern modulating boilers it is important to pay special attention to
gas pressure regulation.
Important:
Check gas supply pressure to each boiler with a manometer or other high-
quality precision measuring device. Pressure should be monitored before firing the boiler,
during operation throughout the boiler's full modulation range, and after the call when the
regulator is in a "lock-up" condition.
Pay special attention to retrofit situations where existing regulators may have an over-
sized orifice and/or worn seats, causing pressure “creep” and high lock-up pressures.
A high quality regulator will maintain constant pressure above the boiler’s minimum
specification at all firing rates, and will not exceed the boiler’s maximum pressure rating
when locked-up with no load.
3.12.1 Gas pressure
The boilers require a minimum inlet gas supply pressure of 4.0" w.c. for natural gas or propane
during high fire operation. For either fuel, the inlet pressure shall be no greater than 14.0" w.c.
Confirm this pressure range is available with your local gas supplier.
The inlet gas connection to the boiler is ¾" NPT (female).
Adequate gas supply piping must be installed with no smaller than ¾" Schedule 40 (e.g., Iron Pipe
Size (IPS) and using a 1" w.c. pressure drop, in accordance with the following table.
Maximum Pipe Length (ft)
Model
¾" IPS
1" IPS
1 ¼" IPS
1 ½" IPS
SL 26-260 G3 (Natural Gas)
20'
80'
300'
600'
SL 26-260 G3 (Propane)
70'
200'
800'
1600'
SL 40-399 G3 (Natural Gas)
10'
40'
150'
300'
SL 40-399 G3 (Propane)
30'
100'
400'
900'
Table 10
Maximum Gas Pipe Length (ft)
55
3.12 Gas piping
Summary of Contents for SL Series
Page 8: ...Intentionally left empty...
Page 12: ...Figure 5 Top view SL 40 399 G3 Figure 6 Bottom view SL 40 399 G3 8 Section Specifications...
Page 14: ...Intentionally left empty...
Page 64: ...Figure 40 Electric wiring connections 60 Section Installation...
Page 76: ...Intentionally left empty...
Page 96: ...Intentionally left empty...
Page 108: ...Intentionally left empty...
Page 110: ...Internal wiring diagram Figure 46 Internal wiring diagram 106 Section Appendices...
Page 111: ...Sequence of operations Figure 47 Sequence of Operation 107 Sequence of operations...