Boiler
Component
Maintenance Required
Frequency
Check
establish a reasonable burner inspection
schedule. Some boiler / locations may call for
annual service, others showing clean burners will
only need attention every 2 – 5 years.
c. Reassemble. Visually inspect the burner through
sight glass. Ensure the flame is stable, without
excessive fluttering. Normal flame pattern is
evenly distributed over the burner surface.
If the burner is operating improperly, remove and clean
or replace. Use a CO
2
analyzer to determine proper
combustion. See
Combustion test target ranges - CO2 /
for correct values.
Annually
□
Heat
exchanger
In areas of poor gas quality, there may be a build-up of
black plaque (typically sulfur). Other fouling agents
include: airborne dust, debris and volatiles.
With the burner removed, examine the heat exchanger
for signs of contamination and clean if necessary.
Annually
□
Boiler Pump
Check that the pump is on in normal operation and that
the water Δ°T is reasonable for a given firing rate.
Annually
□
Gas Piping
Check for damage or leaks and repair as needed.
Annually
□
Boiler
treatment
Check consistency of any boiler treatment used, for
appropriate mixture. Chemical inhibitors are consumed
over time, lowering their density.
Annually
□
Verify proper operation after servicing.
Caution
Installers should inquire of local water
purveyors as to the suitability of their supply
for use in hydronic heating systems.
If water quality is questionable, a local water
treatment expert must be consulted for
testing, assessment and, if required,
treatment.
Alternatively, water or hydronic fluid of known
quality can be brought to the site.
Annually
□
75
7.2.2 General boiler maintenance
Summary of Contents for SL Series
Page 8: ...Intentionally left empty...
Page 12: ...Figure 5 Top view SL 40 399 G3 Figure 6 Bottom view SL 40 399 G3 8 Section Specifications...
Page 14: ...Intentionally left empty...
Page 64: ...Figure 40 Electric wiring connections 60 Section Installation...
Page 76: ...Intentionally left empty...
Page 96: ...Intentionally left empty...
Page 108: ...Intentionally left empty...
Page 110: ...Internal wiring diagram Figure 46 Internal wiring diagram 106 Section Appendices...
Page 111: ...Sequence of operations Figure 47 Sequence of Operation 107 Sequence of operations...