65
6.0 Boiler operation
Before operating the appliance, there are some important pre-igntion checks that need to be
performed. For more information, see
Before operating the boiler on page 63
. To understand the
boiler start-up process, see
Sequence of Operation on page 107
6.1 Lighting and shutting down the boiler
Start-up Checklist
Check
Followed lighting and shutting down procedure.
□
Tested the ignition safety shutoff function (see
Testing the ignition safety shutoff on page
□
Checked the appliance's fuel source, and if necessary,
using
the appropriate P-kit.
□
Performed gas pressure test by
measuring the inlet gas pressure
□
Summary of Contents for SL Series
Page 8: ...Intentionally left empty...
Page 12: ...Figure 5 Top view SL 40 399 G3 Figure 6 Bottom view SL 40 399 G3 8 Section Specifications...
Page 14: ...Intentionally left empty...
Page 64: ...Figure 40 Electric wiring connections 60 Section Installation...
Page 76: ...Intentionally left empty...
Page 96: ...Intentionally left empty...
Page 108: ...Intentionally left empty...
Page 110: ...Internal wiring diagram Figure 46 Internal wiring diagram 106 Section Appendices...
Page 111: ...Sequence of operations Figure 47 Sequence of Operation 107 Sequence of operations...