Preparing to set up your preinstalled server
Use the information to understand the prerequisites that are required for setting up the preinstalled
server.
Attention:
v
Attach an electrostatic discharge (ESD) wrist strap to an unpainted metal surface of your hardware to
prevent the electrostatic discharge from damaging your hardware.
v
When using an ESD wrist strap, follow all electrical safety procedures. An ESD wrist strap is used for
static control. It does not increase or decrease your risk of receiving electric shock when using or
working on electrical equipment.
v
If you do not have an ESD wrist strap, just prior to removing the product from ESD packaging and
installing or replacing hardware, touch an unpainted metal surface of the system for a minimum of 5
seconds.
You might need to read the following documents before you begin to install the server:
v
Installing the IBM Power System E850 (8408-44E) (http://www.ibm.com/support/knowledgecenter/
POWER8/p8eiw/p8eiw_kickoff.htm).
v
To plan your server installation, see Planning for the system (http://www.ibm.com/support/
knowledgecenter/POWER8/p8had/p8had_8xx_kickoff.htm).
v
If you are using a Hardware Management Console (HMC), see Obtaining and applying machine code
updates for the HMC with an Internet connection (http://www.ibm.com/support/knowledgecenter/
POWER8/p8hai/area3fixeshmc.htm).
Consider the following prerequisites before you install the server:
1.
Ensure that you have the following items before you start your installation:
v
Phillips screwdriver
v
Flat-head screwdriver
v
Wire cutter
2.
Ensure that you have one of the following consoles:
v
Hardware Management Console (HMC): Ensure that your HMC is at version 8 release 8.6.0, or
later.
v
Graphic monitor with keyboard and mouse.
v
Teletype (tty) monitor with keyboard.
Completing inventory for your preinstalled server
Use this information to complete inventory for your server.
To complete the inventory, complete the following steps:
1.
Verify that you received all the boxes you ordered.
2.
Unpack the server components as needed.
3.
Complete a parts inventory before you install each server component by following these steps:
a.
Locate the inventory list for your server.
b.
Ensure that you received all the parts that you ordered.
Note:
Your order information is included with your product. You can also obtain order
information from your marketing representative or the IBM Business Partner.
If you have incorrect, missing, or damaged parts, consult any of the following resources:
v
Your IBM reseller.
v
IBM Rochester manufacturing automated information line at 1-800-300-8751 (United States only).
Installing the IBM Power System E850C (8408-44E)
27
Summary of Contents for E850C
Page 1: ...Power Systems Installing the IBM Power System E850C 8408 44E GI11 9920 00 IBM...
Page 2: ......
Page 3: ...Power Systems Installing the IBM Power System E850C 8408 44E GI11 9920 00 IBM...
Page 6: ...iv Power Systems Installing the IBM Power System E850C 8408 44E...
Page 16: ...xiv Power Systems Installing the IBM Power System E850C 8408 44E...
Page 54: ...38 Power Systems Installing the IBM Power System E850C 8408 44E...
Page 67: ...Notices 51...
Page 68: ...IBM Part Number 29R2425 Printed in USA GI11 9920 00 1P P N 29R2425...