26. Install the shipping screws (optional step required only for preventing non-operating transportation
shock/vibration)
The figure above identifies an installed shipping screw using a red arrow. A shipping screw installs
above each of the crossbar thumbscrews as shown in the enclosure rear panel view included above
this step.
Note: After the enclosure is secured in the rack, install the disks.
Routing cables using the CMA
About this task
Routing of power and data cables for the JBOD is integral to successful rail kit installation and rackmount
installation of the enclosure. Cables must be correctly installed and routed to facilitate efficient operation
and in-rack servicing of the enclosure.
This procedure describes the routing of cables through the CMA, including using the CMA baskets and the
CMA storage shelf located at the rear of the enclosure.
Procedure
1. Install the data cables and route them through the CMA brackets.
a) Rotate the CMA cable capture arms so they are out of the way of the data cable routing.
b) Route data cables 1–5 onto the CMA shelf and through the CMA brackets in the order and
configuration shown below.
c) Secure the routed cables with one hand, while installing additional cables until data cables 1–5 are
installed.
d) Rotate the outer cable capture arm close over data cables 1–5, ensuring it seats in the C-flange in
between the two cable capture arms.
Note: This model of the Disk Enclosure does not contain an IOM in slot 1. Thus, disregard the red
cables in the figures below.
38 IBM Cloud Object Storage System: Medium/Large J11/J12 Disk Enclosure Hardware Installation and
Maintenance Manual
Summary of Contents for Medium J11
Page 15: ...European Community and Morocco Notice Germany Notice Safety and environmental notices xv...
Page 103: ......
Page 104: ...IBM...