Running the Checkout Test from the Support Element
Skip this step if you ran Checkout test from a Single Object Operation
1 Before you Start
Checkout test runs at different levels based on the
generation of machine. To avoid confusion and to
ensure the test runs correctly log Off the Hardware
Management Console go to the location of the
Support Element and log On to the Support
Element. When Checkout test is complete return
to the Hardware Management Console to complete
the installation.
1. Open
Task List
from the
Views
area
2. Open
Service
from the
Task List Work
Area
3. Open
Groups
from the
Views
area
4. Select
CPC
from the
Groups Work Area
5. Drag and drop the selected objects on
Checkout Tests
in the
Service
area.
The Confirm the Action panel displays.
6. Select
Run test
The Checkout Test Progress panel
displays.
When complete, a message stating that the
test is complete appears. If the test fails,
double click on the line that says “failed” to
obtain more information. Select
Ok
to exit
results.
7. To exit the test select
OK
from the
Checkout Tests Progress panel.
The Activate tested CPC's panel displays
with a warning message stating that an
activation must be performed.
Do Not
attempt to activate at this time.
8. Select
OK
from the panel.
9. Open
Console Actions
From the
Views
area.
10. Select
Log off
from the
Console Actions
Work Area
.
The Service Mode is active panel displays.
11. Select
No
Optional
Before beginning the test you may want
to double click the left mouse button on each
defined CPC to set status colors for each CPC.
The customer may change these colors after the
installation is complete and the machine is turned
over to the customer.
Note:
If errors were detected consult
Hardware
Messages
for details.
6-30
Installing the System
Summary of Contents for Multiprise 3000 S/390
Page 1: ...S 390 Multiprise 3000 Enterprise Server R IBM Installation Manual SY24 6154 03...
Page 2: ......
Page 3: ...S 390 IBM Installation Manual SY24 6154 03...
Page 8: ...vi Installing the System...
Page 14: ...xii Installing the System...
Page 34: ...1 20 Installing the System...
Page 40: ...2 6 Installing the System...
Page 78: ...5 20 Installing the System...
Page 156: ...6 78 Installing the System...
Page 160: ...7 4 Installing the System...
Page 172: ...B 4 Installing the System...
Page 173: ......
Page 175: ...Spine information IBM S 390 Installation Manual...