Table 7. Common installation SRCs (continued)
SRC
Error description
Recovery steps
11002613
Your power voltages do not
match
Ensure that you are using the correct power voltage.
Refer to your server's specifications to learn more about
the power voltage that your server requires.
Starts with 27xxx,
28xx, 57xxx
and ends with
xxxx3120, xxxx3121
Fibre Channel port failure
These errors are often caused by ports that are not used.
Every port must have a cable or wrap plug installed.
Whenever a cable is not installed, ensure a wrap plug is
installed for each unused port. Wrap plugs are shipped
automatically when a Fibre Channel feature code is
ordered.
B1A38B24
Network configuration
Ensure that you have entered the correct IP address.
Best practices for integrating cable and system placement
These guidelines ensure that your system and its cables have optimal clearance for maintenance and
other operations. The guidelines also provide guidance in correctly cabling your system and using the
appropriate cables.
The following guidelines provide cabling information for installing, migrating, relocating, or upgrading
your system:
v
Position drawers in racks to allow enough space, where possible, for cable routing on the bottom and
top of the rack, and between drawers.
v
Shorter drawers should not be placed between longer drawers in the rack (for example, placing a
19-inch drawer between two 24-inch drawers).
v
When a specific cable plugging sequence is required, for example, for concurrent maintenance
(symmetric multiprocessing cables), label the cables appropriately and note the sequence order.
v
To facilitate cable routing, install cables in the following order:
1.
System power control network (SPCN) cables
2.
Power cables
3.
Communications (serial attached SCSI, InfiniBand, remote input/output, and peripheral component
interconnect express) cables
Note:
Install and route the communications cables, starting with the smallest diameter first and
then progressing to the largest diameter. This applies to installing them into the cable management
arm and retaining them to the rack, brackets, and other features that may be provided for cable
management.
v
Install and route the communications cables, starting with smallest diameter first and then progressing
to the largest diameter.
v
Use the innermost cable-management bridge lances for SPCN cables.
v
Use the middle cable-management bridge lances for power and communications cables.
v
The outermost row of cable-management bridge lances are available for use when routing cables.
v
Use the cable raceways on the sides of the rack to manage excess SPCN and power cables.
v
There are four cable-management bridge lances on the top of the rack. Use these bridge lances to route
the cables from one side of the rack to the other, by routing to the top of the rack, where possible. This
routing helps to avoid having a cable bundle that blocks the cable exit opening at the bottom of the
rack.
v
Use the cable management brackets provided with the system to maintain concurrent maintenance
routing.
32
Power Systems: Installing the IBM Power 710 Express (8231-E1C) or IBM Power 730 Express (8231-E2C)