4.
Determine to place the system in the rack. Record the EIA location.
5.
Facing the front of the rack and working from the right side, use tape, a marker, or pencil to mark
the lower hole of each EIA unit.
6.
Repeat step 5 for the corresponding holes located on the left side of the rack.
7.
Go to the rear of the rack.
8.
On the right side, find the EIA unit that corresponds to the bottom EIA unit marked on the front of
the rack.
9.
Mark the bottom EIA unit.
10.
Mark the corresponding holes on the left side of the rack.
Installing the 8348-21C system by using slide rails
If you ordered the system with the slide rail option, read this section to install the system into the rack by
using slide rails.
Figure 1. Removing the filler panels
4
Installing the System and Ordered Parts for the 8348-21C
Summary of Contents for Power Systems S812LC 8348-21C
Page 2: ......
Page 6: ...iv Installing the System and Ordered Parts for the 8348 21C...
Page 16: ...xiv Installing the System and Ordered Parts for the 8348 21C...
Page 76: ...or or 1 2 3 4 or 1 2 3 4 or 60 Installing the System and Ordered Parts for the 8348 21C...
Page 88: ...72 Installing the System and Ordered Parts for the 8348 21C...
Page 108: ...92 Installing the System and Ordered Parts for the 8348 21C...
Page 109: ......
Page 110: ...IBM Printed in USA...