Figure 27. Packaging for fascia
1
4U fascia (front)
2
1U fascia (power supply units)
fascia: 2077-92F, 2077-A9F ” on page 43.
13. Install the drives, as described in “Installing or replacing a drive: 2077-92F, 2077-A9F ” on page
14. Replace the top cover, as described in “Installing or replacing the top cover: 2077-92F, 2077-A9F ”
15. Lower the mechanical lift so that you can remove the remaining foam blocks away from the
expansion enclosure.
16. Slide the latch on the side of each rail and push the expansion enclosure securely into the rack, as
described in steps “5” on page 51 through “7” on page 51 in “Installing an optional 5U SAS
expansion enclosure” on page 49.
17. Remove the cable management arm assembly from its packaging (
2
18. Attach the cable management arm, as described in “Installing or replacing the cable-management
arm: 2077-92F, 2077-A9F ” on page 51.
19. Connect the SAS cables, as described in “Removing and installing a SAS cable: 2077-92F, 2077-
20. Connect the power cables.
Removing the top cover: 2077-92F, 2077-A9F
To complete some service tasks, you might need to remove the top cover from a 2077-92F, 2077-A9F
(5U) expansion enclosure.
Before you begin
Important: You can remove the cover without powering off the expansion enclosure. However, to
maintain operating temperature, replace the cover within 15 minutes of its removal. When the cover is
removed, the reduction in airflow through the enclosure might cause the enclosure or its components to
shut down to protect from overheating.
38 Storwize V5100 : Quick Installation Guide for MTM 2078-424, 2078-12F, 2078-24F, 2078-92F, and 2078-
U5B
Summary of Contents for Storwize V5100 MTM 2078-424
Page 143: ......