SEQUENCE OF OPERATIONS
12
CONTROL BOARD - FREEZE CYCLE
A quick press of the POWER button on the Push Pad or Board will start the Freeze cycle. The Water Inlet
Valve will be energized (R4 LED on Board illuminated) and water will begin flowing into the Sump. As the
water rises, the contacts in the Low Water Float will open (Switch LED off). The Water Inlet Valve will
remain energized until the High Water Float contacts open (Switch LED off). The Water inlet Valve will be
de‐energized (R4 LED on Board off).
Note: Minimum Freeze Cycle ‐ 5 minutes (from Compressor Start.)
Maximum Freeze Cycle ‐ 1 hour.
BROWN
BLUE
VIOLET
BLACK
RED
TAN
PINK
YELLOW
= Illuminated LED
WHITE
WHITE
BLUE w/ WHITE
BLUE w/ RED
BLUE
12V DC Switches
Line Voltage
Components
R1
R2
R3
R4
R5
R6
Summary of Contents for CIM Series
Page 31: ...ELEVATION SERIES CIM CUBERS BOARD COMPONENT LED SEQUENCE 29 INITIAL HARVEST CYCLE AT START UP ...
Page 32: ...ELEVATION SERIES CIM CUBERS BOARD COMPONENT LED SEQUENCE 30 TRANSITION FROM HARVEST TO FREEZE ...
Page 33: ...ELEVATION SERIES CIM CUBERS BOARD COMPONENT LED SEQUENCE 31 BIN FULL CURTAIN OR STAT ...
Page 35: ...ELEVATION SERIES CIM CUBERS BOARD COMPONENT LED SEQUENCE 33 DIAGNOSTICS IN HARVEST CYCLE ...
Page 36: ...ELEVATION SERIES CIM CUBERS BUTTON FUNCTIONS 34 Button Functions ...