Top Weight Adjustment
Tools required: 5/32” hex key
1. If the cable needs to be shortened 3/4 in. (2 cm)
or more, follow the instructions in steps 1 and 2
on page 8; then, go to step 2 below.
2. Lift the coupler cover from the top weight coupler.
Loosen but do not remove the two set screws in
each side of the weight coupler.
3. Pull the cable out of the top weight coupler.
Determine the amount that the cable needs to be
shortened, and cut that much off the end of the
cable.
The cable must be long enough to be
held by the set screws without lifting the top
weight.
4. Cut the cable to the desired length and strip 1 in.
(2.5 cm) of the vinyl sheath from the cut end of
the cable.
5. Insert the cable into the top weight coupler until all
four set screws can be tightened against the
cable. Tighten each set screw alternately 1/4 turn,
until all are set to 150 inch/pounds (17 Newton-
meters).
6. Lower the coupler cover over the top weight cou-
pler.
7. Slowly perform a repetition using a light load and
have someone make sure that the cable is not
derailed from a pulley or rubbing on a cable trap.
Press Frame Pulley Adjustment
Tools required: Adjustable wrench
1. Lift the top weight off the
weight stack and insert the
weight pin into the next
weight and the sixth hole
from the top of the weight
selector.
2. Loosen, but do not remove, the indicated nut.
3. To remove slack from the cable, move the pulley
(not shown) to the top of the indicated slot.
To add slack to the cable, move the pulley (not
shown) to the bottom of the indicated slot.
4. Retighten the nut.
5. Lift the top weight and remove the weight pin.
Lower the top weight onto the next weight.
6. Readjust as necessary.
7. Slowly perform a repetition using a light load and
have someone make sure that the cable is not
derailed from a pulley or rubbing on a cable trap.
Top
Nut
Slot
Pulley
Bottom
Set Screws
Cable
Top Weight
Coupler
Coupler Cover