INSTALLATION
Buccaneer GT Range
- Installation
15
- Remove the convection accelerators
(only for boilers with 3, 4 and 5 sections)
- Sweep carefully the upper flues and the hearth with the
brush provided
- Remove the spot from the hearth with a vacuum cleaner
- Replace the convection accelerators
- Close the door and replace the front cover
PRECAUTIONS TO BE OBSERVED IN CASE
OF PROLONGED STOPPAGE OF THE BOILER
- Have the boiler and the chimney carefully swept. Shut the
boiler doors to avoid any air flow inside.
- If the boiler is going to be stopped for several months, we
also advise removing the pipe which connects the boiler
to the chimney and to close off the nozzle with a cover.
- In case of stoppage of the heating in winter leading to risks
of freezing, we advise the use of a concentrated anti-freeze
agent to prevent the heating water from freezing.
Otherwise, completely drain the installation (in this case,
the slot of the valve screw on the load pump must be
positioned vertically. The tank and the sanitary hot water
piping must also be drained.