2
icos
-
Users
Introduction
The
icos
is a wall mounted, room sealed, super efficient
condensing boiler featuring full sequence automatic spark
ignition and fan assisted combustion.
Due to the very high efficiency, condensate is produced from
the flue gases and this is drained to a suitable disposal point
through the plastic waste pipe at the right lower rear of the
boiler. A condensate 'plume' will also often be visible at the
flue terminal.
S a f e t y
Current Gas Safety (Installation & Use)
Regulations or rules in force.
In your own interest, and that of safety, it is the law that this boiler
must be installed by a Gas Safe Registered Engineer.
In IE the installation must be carried out by a Registered Gas
Installer (RGII) and installed in accordance with the current
edition of I.S. 813 “domestic Gas Installations”, the current
Building Regulations and reference should be made to the
current ETCI rules for electrical installation.
It is essential that the instructions in this booklet are strictly
followed, for safe and economical operation of the boiler.
Electricity Supply
The appliance must be earthed.
Supply 230 V - 50 Hz. The fusing should be 3A.
This appliance is intended to be connected to the supply via a
double-pole switch, having a 3mm contact separation in both
poles, serving only the boiler and system controls. Alternatively, a
3-pin UNSWITCHED socket may be used.
Important Notes
z
This appliance must not be operated without
the casing correctly fitted and forming an adequate seal.
z
If the boiler is installed in a compartment then the compartment
MUST NOT be used for storage purposes.
z
Under NO circumstances should any of the sealed components
on this appliance be used incorrectly or tampered with.
z
If it is known or suspected that a fault exists on the boiler
then it MUST NOT BE USED until the fault has been
corrected by a Gas Safe Registered Enginner or in IE a
Registered Gas Installer (RGII).
z
This appliance is not intended for use by persons (including
children) with reduced physical, sensory or mental
capabilities, or lack of experience and knowledge, unless
they have been given supervision or instructions concerning
use of the appliance by a person responsible for their safety.
Destination Countries: GB, IE
icos HE12, HE15, HE18, HE24
(Natural Gas Only)
HE12
G.C. Appliance No. 41-397-95
HE15
G.C. Appliance No. 41-397-83
HE18
G.C. Appliance No. 41-397-84
HE24
G.C. Appliance No. 41-397-85
z
Children should be supervised to ensure that they do not play
with the appliance.
In cases of repeated or continuous shutdown a Gas Safe
Registered Engineer or in IE a Registered Gas Installer (RGII)
should be called to investigate and rectify the condition causing
this and carry out an operational test after each intervention on
the device. Only the manufacturers original parts should be used
for replacement.
Minimum Clearances
Clearances of
165mm (6 1/2"
) above,
100mm (4"
) below,
5mm
(1/4"
) at the sides and
450mm (17 3/4
") at the front of the boiler
casing must be allowed for servicing.
The minimum front and bottom clearance allowed when built into
a cupboard is 5mm.
To light the boiler
(Refer to Frame 1)
1.
CHECK THAT THE ELECTRICITY SUPPLY TO THE BOILER
IS OFF.
2.
Set the mains on/off switch (A) to off and the CH thermostat
knob (C) to maximum.
3.
Switch on the electricity supply to the boiler and check that all
external controls, e.g. programmer, room thermostat, etc are on.
4.
Set the mains on/off switch to ON.
The boiler will commence the ignition sequence, supplying heat
to the system when required.
Operation
In normal operation the control unit display (F) will show the
codes:
- Standby
(no demand for heat)
- CH or DHW being supplied
- Boiler Frost Protection
(Boiler will fire if temperature is less
than 3 degrees C.
During
ignition
the LED (E) will flash.
During
normal running
the LED will remain illuminated.
Note.
If the boiler fails to light after 3 attempts the fault code 'L' 'F'
will be displayed.
Press and hold the reset button for 2 seconds then release. The
boiler will repeat the ignition sequence. If the boiler fails to light
consult a Gas Safe Registered Engineer or in IE a Registerd Gas
Installer (RGII).
All Gas Safe Registered Engineers carry a Gas Safe Register ID card, and have a registration number. Both should be recorded
in the
Benchmark
Commissioning Checklist. You can check your installer by calling Gas Safe Register direct on 0800 4085500
THE BENCHMARK SERVICE INTERVAL RECORD MUST BE COMPLETED AFTER EACH SERVICE
Ideal Stelrad Group
is a member of the Benchmark scheme and fully supports the aims of
the programme. Benchmark has been introduced to improve the standards of installation and
commissioning of central heating systems in the UK and to encourage the regular servicing of
all central heating systems to ensure safety and efficiency.
back