SERVICING
User control
Screws
Ecl 2103
Note.
Only the display unit is replaced.
1.
Refer to Frame 51.
2.
Loosen the securing screw on the underside of the user
control.
3.
Pull the display unit forward to remove.
4.
Push the new display unit into position.
5.
Re-assemble in reverse order.
6.
Check operation of the boiler. Refer to Frame 51.
65 USER CONTROL REPLACEMENT
66 PRESSURE GAUGE REPLACEMENT
1.
Refer to Frame 51.
2.
Drain the boiler. Refer to Frame 69.
3.
Unscrew the pressure gauge and discard.
4.
Fit the new pressure gauge using a suitable jointing
compound.
5.
Refill the boiler. Refer to Frame 29.
6.
Check operation of the boiler. Refer to Frame 51.
2041
Pressure gauge
Flow isolation valve
(shown in the open position)
Ecl 1779
Securing
screw
Display
unit