The boiler does not normally need a bypass but at least
some radiators on the heating circuit, of load of at least 10%
of the minimum boiler output, must be provided with twin
lockshield valves so that this minimum heating load is always
available. See note regarding thermostatic radiator valves on
page 10.
Note.
Systems incorporating zone valves which could
completely cut off the flow through the system must also
include a bypass.
Balancing
1. Set the programmer to ON.
Close the manual or thermostatic valves on all radiators,
leaving the twin lockshield valves (on the radiators
referred to above) in the OPEN position.
Turn up the room thermostat and adjust the lockshield
valve to give an uninterrupted flow through the radiator.
These valves should now be left as set.
2. Open all manual or thermostatic radiator valves and
adjust the lockshield valves on the remaining radiators, to
give around 20
o
C temperature drop at each radiator.
3. Adjust the room thermostat and programmer to
NORMAL
settings.
1.17 WATER TREATMENT
1.16 SYSTEM BALANCING
Central Heating
The Logic range of boilers have an
ALUMINIUM
alloy heat
exchanger.
IMPORTANT
The application of any other treatment
to this product may render the guarantee of Ideal Heating
invalid.
Ideal Heating
recommend Water Treatment in accordance
with the Benchmark Guidance Notes on Water Treatment in
Central Heating Systems.
If water treatment is used
Ideal Heating
recommend only the
use of
SCALEMASTER SM-1 PRO, FERNOX, MBI, ADEY MC1,
SENTINEL X100 or CALMAG CM100
inhibitors and associated
water treatment products, which must be used in accordance
with the manufacturers’ instructions.
This boiler can be used with a water softener. However, the
heating system should not be filled with softened water as
any softening chemicals could enhance corrosion of certain
materials in the heating system, including aluminium and
steel. The heating system should always be filled from the
bypass on the water softener installation.
Notes
1.
It is most important that the correct concentration of the
water treatment products is maintained in accordance
with the manufacturers’ instructions.
2.
If the boiler is installed in an existing system any
unsuitable additives MUST be removed by thorough
cleansing. BS7593:2019 details the steps necessary to
clean a domestic heating system.
3.
In hard water areas, treatment to prevent lime scale may
be necessary - however the use of artificially softened
water is NOT permitted.
4.
Under no circumstances should the boiler be fired before
the system has been thoroughly flushed.
For further information contact:
Fernox
www.fernox.com
Tel: +44 (0) 3301 007750
Sentinel Performance Solutions
www.sentinelprotects.com
Tel: +44 (0) 1928 704330
Scalemaster Water Treatment Products
www.scalemaster.co.uk
Tel: +44 (0) 1785 811636
Calmag Ltd.
www.calmag Ltd.com
Tel: +44 (0) 1535 210320
Adey
www.adey.com
Tel: +44 (0) 1242 546700