INSTALLATION
Mini
Installation & Servicing
25
28 INITIAL LIGHTING
Legend
A Appiance operation lamps
B Domestic hot water temperature control
Mini C24
,
Mini C28
,
Mini C32
B Service knob
Mini S24
,
Mini S28
C Main switch and radiator temperature control
D Boiler reset button
E Lock---out signal lamp
F Programmer (optional) for
Mini C24
,
Mini C28
,
Mini C32
boilers only.
G System pressure and temperature gauge
A
Central Heating flow
Domestic hot
water outlet
Gas inlet
Domestic cold
water inlet
Central Heating return
Mini C24
Mini C28
Mini C32
Mini S24
Mini S28
Mini C shown
E
B
C
D
F
G
IMPORTANT Before lighting the boiler you should note
especially that:
1 Check that all the drain cocks are closed and any valves
in the flow and return are open.
2 Check that the system has been filled and pressurised
and that the boiler is not air locked.
3 Remove boiler front panel.
4 Ensure that the pump is free to rotate
i
Remove the vent plug
ii Using a screwdriver, rotate the shaft several times
iii Replace the vent plug
Note
. Some slight water leakage will occur
5 Remove the screw in the burner pressure test point
indicated on the following picture and connect a gas
pressure gauge via a flexible tube.
Be sure to select the correct pressure test point. Refer to
Tables for pressures.
6 Check that the gas service cock is ON.
7 Switch the electricity supply ON and check that all
external controls are calling for heat.
8 Set the main switch C to ’ON’. Following a pre---purge
period the gas control solenoid valve should open and the
spark commence, continuing until the burner is
established.
9 Check that the burner lights smoothly. If this does not
occur within 20 seconds, turn the main switch to ’O’
position, wait for 5 seconds then try again by pressing the
reset button ’D’. If the burner still does not light, refer to
the ’Fault Finding’ section.
10 Test for gas soundness around ALL boiler gas
components, using leak detection fluid.
11 Operate the boiler for 10 minutes to stabilise the burner
temperature.
12 Check that the burner pressures are correct. The boiler is
factory pre---set and should not need adjustment.
However if adjustment is required refer to frame 29.
13 Set the boiler main switch to ’O’.
14 Remove the pressure gauge and tube. Replace the
sealing screw in the pressure test point. Ensure a gas
tight seal is made.
15 Refit the boiler front panel using the screws previously
removed.
16 Switch the boiler on again.
INST
ALLA
TION