1.13 BOILER CLEARANCES AND CONNECTIONS
The following minimum clearances must be
maintained for operation and servicing.
Front of boiler - 450mm
Sides of boiler - 25mm
Above boiler - dependent upon the flue
system see drawings
Below boiler - 300mm
Clearance between multiple boiler
installations - 25mm
80/125 CONCENTRIC FLUE CONNECTOR
30, 40, 60 & 80
Minimum boiler top clearances:
for vertical flue 200mm
for horizontal flue 350mm (415mm for 100/150)
for open flue 350mm
100/150 CONCENTRIC FLUE CONNECTOR
100, 120 & 150
Minimum boiler top clearances:
for vertical flue 200mm
for horizontal flue 370mm
for open flue 350mm
Flue centre line
=194.5 (80/125) =259.5 (100/150)*
* with 100/150 adaptor
(See Frame 13)
Flue centre line
=202
FLOW &RETURN CONNECTIONS
81
GAS & CONDENSE OUTLETS
68
B
500
59
59
209
299
A
118
850
RETURN
GAS
CONDENSE
FLOW
Boiler
Dim. A
Dim. B
30, 40, 60, 80
360
130
100, 120
520
226
150
610
233
OPEN FLUE KIT
100 / 150
OPEN FLUE KIT
80 / 125
ima5400
X
Y
26
52
78
104
Vertical Offset From X mm
Distance from flue centre line (Y) to outside wall surface.
For lengths greater than 4m, increase offset (X) by 26mm
for every additional 1m.
4m
3m
2m
1m
100
83
148.5
80
83
125
12
Installation & Servicing
SECTION 1 - GENERAL
Summary of Contents for EVOMAX 2 30
Page 4: ...4 Installation Servicing...
Page 75: ...75 Installation Servicing NOTES...
Page 76: ...76 Installation Servicing NOTES...
Page 77: ...77 Installation Servicing NOTES...
Page 78: ...78 Installation Servicing NOTES...