INSTALLATION STEPS 

To install the RACK-3200G chassis, the following installation steps 
must be completed: 

Step 1: 

Unpack the chassis. 

Step 2: 

Install the front handles. 

Step 3: 

Remove the top cover. 

Step 4: 

Install the rear panel serial port, parallel port and PS/2 
connectors. 

Step 5: 

Install the PSU. 

Step 6: 

Install the backplane. 

Step 7: 

Install the CPU card. 

Step 8: 

Install the PCI and ISA expansion cards. 

Step 9: 

Install the disk drives. 

Step 10: 

Front panel cables. 

Step 11: 

PSU cable and interface cable connections. 

Step 12: 

Cover reinstallation.

Step 0:

 

 
The installation steps outlined above are described in detail below. 
Please refer to the relevant section. 

STEP 1: UNPACK 

The RACK-3200G is shipped in a plastic bag that is placed inside a 
cardboard box. The accessories are also shipped with the chassis. 
When you unpack the chassis you must: 
 

 

Make sure all the items listed in the 

PACKING LIST

 section 

above are present. 

 

Make sure the chassis has not been damaged in anyway. 

STEP 2: FRONT HANDLE INSTALLATION 

Two handles are shipped with the RACK-3200G chassis. The 
handles are installed on the sides, at the front of the chassis. Each 
handle is secured to the chassis by four retention screws. To install 
the handles, please follow the steps below. 

Step 1: 

Align the retention screw holes on the side of the chassis 
with the retention screw holes in the handle. 

Step 2: 

Insert the retention screws.

Step 0:

 

 

Figure 2: Front Handle Retention Screws 

STEP 3: REMOVE THE TOP COVER 

The top cover of the chassis is secured to the chassis with eight 
retention screws, four on each side. To remove the top cover, please 
follow the steps below. 

Step 1: 

Remove all eight top cover retention screws. Remove four 
retention screws from each side of the chassis. 

Figure 3: Top Cover Retention Screws 

Step 2: 

Slide the cover backwards and then lift it up gently. 

Step 0:

 

Figure 4: Remove the Top Cover 

STEP 4: INSTALL THE REAR PANEL 
SERIAL PORT, PARALLEL PORT AND 
PS/2 CONNECTORS 

The rear panel of the RACK-3200G can accommodate: 

2 x serial ports 

3 x parallel ports 

1 x PS/2 connector 

Figure 5: 

  Parallel Port and Serial Port Locations 

 
These ports must be installed before any other components are 
installed. To install these connectors please follow the steps below. 

Step 1: 

Snap off the port covers in accordance with the number 
and type of ports you need.

Summary of Contents for RACK-3200G

Page 1: ...loppy disk drive Dimensions DxWxH o 674mm x 431mm x 176mm Operating Temperature 0 40 C Relative Humidity 5 95 Vibration o 5 17Hz 0 1 double amplitude displacement o 17 640Hz 1 5G acceleration peak to...

Page 2: ...RACK 3200G QIG IEI Technology Corp Page 2 DIMENSION DRAWING The dimensions of RACK 3200G are shown below Figure 1 Dimension Drawing measurement units millimeter...

Page 3: ...3200G chassis The handles are installed on the sides at the front of the chassis Each handle is secured to the chassis by four retention screws To install the handles please follow the steps below Ste...

Page 4: ...stall the PSU Compatible IEI PSUs are listed in the table above NOTE RACK 3200G PSU installation is a complicated process Before you proceed with the installation of the PSU please read all the instal...

Page 5: ...e Figure 10 Remove Two Side Retention Screws and Loosen Two Top Retention Screws Figure 11 Run the Cable through the Right Hole underneath the PSU Bracket Step 8 Insert the PSU into the bracket Make s...

Page 6: ...copper pillars Step 3 Once the backplane is properly aligned with the retention screw holes secure the backplane to the chassis with 15 retention screws Figure 17 Secure the Backplane to the Chassis S...

Page 7: ...the drive bracket retention screw s from the front panel The right side drive bracket has two front panel retention screws The left side drive bracket has one front panel retention screw Figure 20 Dri...

Page 8: ...ey must first be mounted on separately purchased HDD brackets The HDD brackets are accessory items Step 1 Position the HDD onto the HDD bracket Make sure the PCB board of the HDD faces the bottom of t...

Page 9: ...over the chassis and reinsert the eight previously removed retention screws Chassis Maintenance Fan Replacement NOTE Please ensure the power of the computer is switched off before fan replacement proc...

Page 10: ...ep 0 Cabinet Installation Supporting rails rack trays or slide rails can be implemented using the mounting holes on the sides of the chassis The eight mounting holes in the two handles on the sides of...