OPERATION
IC120 ENG
3-20
Lifting the machine
WARNING
ALWAYS lift the machine on the level ground.
NEVER lift the machine loaded with any personnel.
Make sure the lifting cables and other lifting devices are strong enough to support the
machine.
Do not perform crane operation including slinging work unless you are not qualified.
Weight on lifting the machine: 14100 kg
1. Prepare strong enough wire ropes, shackles, sling frame and sling jigs.
2. Fix the sling jigs at the positions of the crawler frame shown above and pass the wire
rope through them.
3. Install the wire rope to the sling frame with the shackle.
4. Install the wire rope to the crane hooks and lift upward so the crawler is a little bit above
the ground, then stop lifting.
5. If the balance is good continue slowing lifting the machine.
Shackle
Sling jig
Sling jig
Sling frame