Horizontal intake kits - exhaust Ø 60/100.

Kit assembly: install the bend with flange (2) on the central 

hole of the boiler inserting the seal (1) 

(which does not require 

lubrication)

, positioning it with the round protrusions down-

wards in contact with the boiler flange and tighten using the 

screws supplied with the kit. Fit the male end (smooth) of 

the Ø 60/100 concentric terminal pipe (3) up to the stop 

on the female end of the bend (2), making sure the relevant 

internal and external rings are fitted; this will ensure hold 

and joining of the elements making up the kit.

N.B.: 

for correct operation of the system the terminal with 

grill must be correctly installed, respecting the indication 

“top” on the terminal.

•  Coupling extension pipes and concentric elbows Ø 60/

100. To install possible coupling extensions on other fume 

extraction elements, proceed as follows: fit the male end 

(smooth) of the concentric pipe or concentric elbow up to 

the stop on the female end (with lip seals) of the previously 

installed element; this will ensure correct hold and joining 

of the elements.

e Ø 60/100 kit can be installed with the rear, right side, 

left side and front outlet.

•  Extensions for horizontal kit. e horizontal intake-ex-

haust kit Ø 60/100 can be extended up to a 

max. horizontal 

length of 12.9 m,

 including the grill terminal and excluding 

the concentric bend leaving the boiler. is configuration 

corresponds to a resistance factor of 100. In this case special 

extensions must be requested.

N.B.:

 when installing the ducts, a section clamp with pin 

must be installed every 3 metres.
•  External  grill. 

N.B.:

  for  safety  purposes,  do  not  even 

temporarily obstruct the boiler intake/exhaust terminal.

Vertical kit with aluminium tile Ø 60/100.

Kit assembly: install the concentric flange (2) on the central 

hole of the boiler inserting the seal (1)

 (not requiring lubrica-

tion)

, positioning it with the round protrusions downwards 

in contact with the boiler flange and tighten using the screws 

supplied  with  the  kit.  Fit  the  male  end  (smooth)  of  the 

adapter (3) in the female end of the concentric flange (2).

Fake aluminium tile installation: replace the tiles with the 

aluminium sheet (5), shaping it to ensure that rainwater runs 

off. Position the fixed half-shell (7) on the aluminium tile 

and insert the intake/exhaust pipe (6). Fit the male end (6) 

(smooth) of the Ø 60/100 concentric terminal up to the stop 

on the female end of the adapter (3) (with lip seals), making 

sure that the ring (4) is already fitted; this will ensure hold 

and joining of the elements making up the kit.

•  Coupling extension pipes and concentric elbows. To install 

possible coupling extensions on other fume extraction ele-

ments, proceed as follows: fit the male end (smooth) of 

the concentric pipe or concentric elbow up to the stop on 

the female end (with lip seals) of the previously installed 

element; this will ensure correct hold and joining of the 

elements.

Important:

 if the exhaust terminal and/or extension con-

centric  pipe  needs  shortening,  consider  that  the  internal 

duct must always protrude by 5 mm with respect to the 

external duct.
is specific terminal enables fume exhaust and air intake 

necessary for combustion, in a vertical direction.

N.B.: 

the vertical kit Ø 60/100 with aluminium tile enables 

installation on terraces and roofs with maximum slope of 

45% (24°) and the height between the terminal cap and 

half-shell (374 mm) must always be respected. 

C13x

C13x

C33x

e kit comprises:

1 -  Seal (1)

1 -  Concentric bend Ø 60/100 (2)

1 -  Concentric intake/exhaust 

terminal Ø 60/100 (3)

1 -  Internal ring (4)

1 -  External ring (5)

e kit comprises:

1 - Seal (1)

1 - Female concentric flange (2)

1 - Adapter from 80/125 

to 60/100 (3)

1 - Ring (4)

1 - Aluminium tile (5)

1 - Intake/exhaust concentric 

pipe Ø 60/100 (6)

1 - Fixed half-shell (7)

1 - Movable half-shell (8)

10

INST

ALLER

USER

TECHNICIAN

11

INST

ALLER

USER

TECHNICIAN

Summary of Contents for VICTRIX ZEUS 20

Page 1: ...GB Instruction booklet and warning Installer User Technician VICTRIX 20 27...

Page 2: ...with the appliance It must be kept in a safe place and read carefully as it contains important information to ensure safe installation use and maintenance Installation and maintenance must be performe...

Page 3: ...ns 18 2 3 Control panel 19 2 4 Restoring heating system pressure 20 2 5 Draining the system 20 2 6 Anti freeze protection 20 2 7 Casing cleaning 20 2 8 Decommissioning 20 3 Boiler start up preliminary...

Page 4: ...quired procedures Before installing the appliance ensure that it is delivered in perfect condition if in doubt contact the supplier immediately Packing materials staples nails plastic bags polystyrene...

Page 5: ...manufacturer declines any responsibility in case of flood ing if the drain valve cuts in Important to preserve the life and efficiency of the domestic circuit exchanger it is advisable to install the...

Page 6: ...on In addition to the functions described in the previous point the Remote Friend Control enables the user to have under control and at hand all the important information regarding appliance and heati...

Page 7: ...set on the Remote Friend Control only if the boiler main switch is turned to Domestic Remote Friend Control Important If the Remote Friend Control is used arrange two separate lines in compliance with...

Page 8: ...tor of the single component does not depend on the type of boiler on which it is installed and is a dimen sional value It is based on the temperature of fluids passing through the ducts and therefore...

Page 9: ...ncentric horizontal intake exhaust 60 100 Intake and exhaust 9 1 4 m Intake and exhaust 5 2 0 8 m Equivalent length in metres of pipe 80 Terminal complete with concentric vertical intake exhaust 60 10...

Page 10: ...t length in metres of pipe 60 Equivalent length in metres of pipe 80 Complete vertical exhaust terminal 60 for ducting Intake 2 2 Exhaust 1 9 Intake 1 9 Exhaust 2 6 Intake 1 2 Exhaust 1 6 Exhaust 3 3...

Page 11: ...boiler inserting the seal 1 not requiring lubrica tion positioning it with the round protrusions downwards in contact with the boiler flange and tighten using the screws supplied with the kit Fit the...

Page 12: ...levant internal and external rings are fitted Fit the male end smooth of the exhaust pipe 9 up to the stop on the female end of the bend 5 making sure that the internal ring is fitted this will ensure...

Page 13: ...system Green Range 60 mm rigid and 80 flexible ducting systems can only be used for domestic use and with Immergas condensing boilers In any case ducting operations must respect the provisions contai...

Page 14: ...s be suitably designed to prevent the possible freezing of condensate inside the fume system and condensate dis charge system trap passivator tank comply with the current relevant national and local r...

Page 15: ...ollowing must be done for boiler start up check gas supply circuit tightness with the 0n Off valve closed and subsequently open with gas valve closed no gas flow must be read on the meter for 10 minut...

Page 16: ...pen adjustment screw fully unscrewed Head kPa A Flowrate l h B C Head m H 2 O Polyphosphate dispenser kit by request e polyphos phate dispenser prevents the formation of scale and preserves the origin...

Page 17: ...with seat for Venturi 13 Electronic control unit 14 Overtemperature safety thermostat 15 Circulating pump 16 Plate type heat exchanger 17 Pump safety pressure switch 18 3 bar safety valve 19 3 way val...

Page 18: ...Electronic control unit 14 Overtemperature safety thermostat 15 Circulating pump 16 Plate type heat exchanger 17 Pump safety pressure switch 18 3 bar safety valve 19 3 way valve monobloc 20 Adjustabl...

Page 19: ...ctrical water and gas supplies In case of work or maintenance to structures located in the vicinity of ducting or fume extraction devices and relevant accessories switch off the appliance and after co...

Page 20: ...iler on Stand by an illuminated horizon tal segment appears on the display In case of malfunction or anomaly the temperature is replaced by the relative error code flashing 1 Ignition block 2 Block du...

Page 21: ...an antifreeze function that starts the pump and the burner when the system water temperature inside the boiler falls below 4 C e anti freeze function is guaranteed if the boiler is fully operative and...

Page 22: ...Control or Room ermostat e boiler is arranged for application of a Room thermostat or the Remote Friend Control C A R Connect the Room ermostat to terminals 40 and 41 and remove jumper X20 e Remote Fr...

Page 23: ...el PTC S1 Main rotary switch S2 Pump flow switch microswitch S3 Domestic circuit priority microswitch T1 Voltage transformer TA Room thermostat On Off optional U1 Rectifier inside gas valve connector...

Page 24: ...stat 18 Automatic air valve 19 Igniters 20 Expansion tank 21 Air intake pipe 22 Circulating pump 23 Circulating pump pressure switch microswitch 24 One way valve 25 Circulating pump pressure switch 26...

Page 25: ...hood 19 Air analyzer chamber 20 p gas pressure point 21 Fume analyzer chamber 22 NTC limit and heating control sensor 23 Overtemperature safety thermostat 24 Automatic air valve 25 Igniters 26 Expansi...

Page 26: ...f CO2 in the fumes with boiler at min output with respect to the following table seal the gas flow regulation devices if the settings are modified after completing conversion apply the sticker include...

Page 27: ...11 Combustion parameters check For max and min heat output adjustment insert the differential manometer between P1 and P2 see fig on page 23 24 for measuring the gas pressure Bring the boiler to chimn...

Page 28: ...the system return water is below 4 C the boiler starts up and functions until reaching 42 C 3 17 System delivery temperature too high By operating the jumper 5 page 28 two delivery temperature ranges...

Page 29: ...mode jumper 5 Heating temperature preselection range 6 RS 232 computer interface VK 4115 V gas valve for Victrix 20 Electronic card 7 Output for fan rpm measurement 8 Max heating power adjustment trim...

Page 30: ...DUNGS gas valve for Victrix 27 Key 1 Gas valve inlet pressure point 2 Gas valve outlet pressure point 3 Off Set adjustment screw 12 Outlet gas flow regulator 29 INSTALLER USER TECHNICIAN...

Page 31: ...he screws 1 on the bottom of the casing front pull the bottom of the casing front outwards while at the same time pushing upwards see fig undo the screws 2 on the top of the casing front support sheet...

Page 32: ...k activation of the device against no gas ionization flame control ensure intervention time is less than ten seconds Visually check for water leaks or oxidation from on con nections and traces of cond...

Page 33: ...14 1 78 18 1 1 12 2 60 26 5 12 0 10320 1 32 1 69 17 3 0 98 1 30 13 3 0 97 1 90 19 4 10 0 8600 1 11 1 23 12 6 0 82 0 91 9 3 0 81 1 40 14 3 8 0 6880 0 89 0 84 8 6 0 67 0 60 6 1 0 66 0 90 9 2 6 0 5160 0...

Page 34: ...low limiter rated delivery min pressure Domestic circuit min pressure dynamic Domestic circuit max working pressure D specific delivery according to EN 625 Drawing capacity in continuous operation T 3...

Page 35: ...x working temperature heating circuit Adjustable heating temperature Pos 1 Adjustable heating temperature Pos 2 Total volume heating expansion tank Heating expansion tank precharge Generator water cap...

Page 36: ...www immergas com ISO 9001 Certified Company is instruction booklet is made of ecological paper Cod 1 021298 Rev 15 017635 000 04 04...

Reviews: