12/89:
PARTS-82
15. Install control rods and cross control rod.
16. Port T1 is located on the valvebank bottom port
next to the base. Remove the plug and screw in plug
#61367. This must be installed to build up pressure
so that the power stabilizers will function correctly.
After installing plug, add fitting #25833. Connect hose
#62848. The other end of the hose will connect to the
two-section valvebank.
17. See top picture. The hose that runs from port T1
on the valvebank will connect to the top port on the
two section valvebank.
See Step 17.
18. Remove return hose from tank. Add fitting
#25828. Reconnect return hose as shown.
20020909
Summary of Contents for 12/89
Page 91: ...12 89 PARTS 91...