For Mod5T 120/30 42U (Battery inside)
Model
30KVA 60KVA 90KVA 120KVA
Current (A)
100
200
300
400
Power cable (mm
2
)
25
95
150
240
Fixation torque force (lb-in)
20
20
20
20
Warning:
1.
When Load is less than 30KVA, at least two layers of battery modules (8 modules) have to be
installed.
2.
When Load is between 30KVA and 60KVA, at least three layers of battery modules (12 modules)
have to be installed.
3.
When Load is between 60KVA and 90KVA, at least five layers of battery modules (20 modules)
have to be installed.
4.
When Load is larger than 90KVA, the external battery cabinet must be installed.
5.
The same type of battery has to be used, if the battery is in parallel application.
For Mod5T 120/30 S 30U, Mod5T 180/30 S 30U, Mod5T 210/30 S 42U and Mod5T 300/30 S 42U
Model
30KVA 60KVA 90KVA 120KVA 150KVA
Current (A)
100
200
300
400
500
Power cable (mm
2
)
25
95
150
240
120 x 2
Fixation torque force (lb-in)
20
20
20
20
20
Model
180KVA 210KVA 240KVA 270KVA 300KVA
Current (A)
600
700
800
900
1000
Power cable (mm2)
150 x 2 240 x 2 240*2
300*2
185*3
Fixation torque force (lb-in)
20
20
20
20
20
2.11 Wiring
WARNING:
Before connecting any wire, make sure the AC input and battery power is completely cut off.
Make sure the breakers, Main Breaker (Q1), Maintenance Breaker (Q2), Output Breaker (Q3)
and battery breaker are all in the OFF position.
Make sure the Maintenance Bypass Switch is in UPS position.
In order to have good heat dissipation, the power cables MUST come into the cabinet from
top of the cabinet. Or the cables will block the cooling ventilation and make the over
temperature failure.