05/20 E&OE
No
.
HIU Commissioning Checklist
Comment and confirm checked
Date
11
Verify and record the Power supply
available.
Check for Earth continuity.
12
Verify and record if the casing is secure
and if all electrical connections are safe
and conform to current wiring
Regulations.
13
Switch ON power supply to the unit
and record if any error codes
Address error codes accordingly and
record actions
14
Ensure the room thermostat setting is
above ambient temperature. Verify
and record the HIU has entered
heating mode.
Return room thermostat back to
original temperature
15
For Underfloor Heating installations
verify and record the central heating
flow temperatures to the pipes into
the floor circuits are as specified by the
system designer. Adjust accordingly if
required and verify and record
Return room thermostat back to
original temperature
16
Open a hot water outlet in the
property, verify and record the
temperature of the hot water from the
outlet
17
Validate and register online warranty
Commissioning Company Name
……………………………………………………………………...
Commissioning Engineer Name
………………………………………………………………………….
Date
Date
Section 7
-
Commissioning
-