Instruction Manual
|
5
T: 303-833-6644
or
800-666-1611
www.inteccorp.com
Original Language - English
Set up and Operation
System Set-Up:
Set system on a dry, level surface.
1.
Obtain appropriate protective equipment.
2.
Attach hose to machine outlet using a hose clamp.
3.
Open slide gate & place pin in desired opening.
Note suggested settings are labeled by slide gate.
4.
Connect 12/3 gauge heavy duty power cords; each power
source is required to be an independent circuit.
A.
120Volt systems: If cannot find three (3) independent circuits, or if desire
is to use 1 blower vs. 2 blowers, then you do not need to connect the
second blower (i.e. only 2 independent circuits required).
B.
220 - 240Volt systems: For EU use, two (2) independent 230 V / 16amp
circuits are required for proper operation.