background image

Specifications are subject to change without notice.

34

441 01 7201 00

b. Insert the twisted wire end of brush into end of spring

cable, and crimp tight with crimping tool or crimp by

striking with ball- peen hammer. TIGHTNESS IS VERY
IMPORTANT.

IGNITER

POSTION

A180230

Fig. 36 - Igniter Position

(1.) Attach variable- speed, reversible drill to the end of

spring cable (end opposite brush).

(2.) Insert brush end of cable into the outlet opening of

cell and slowly rotate with drill. DO NOT force
cable. Gradually insert cable into upper pass of cell.
(See Fig. 37)

(3.) Work cable in and out of cell 3 or 4 times to obtain

sufficient cleaning. DO NOT pull cable with great

force. Reverse drill and gradually work cable out.

(4.) Insert brush end of cable in burner inlet opening of

cell, and proceed to clean two lower passes of cell
in same manner as upper pass.

(5.) Repeat foregoing procedures until each cell in

furnace has been cleaned.

(6.) Using vacuum cleaner, remove residue from each

cell.

(7.) Using vacuum cleaner with soft brush attachment,

clean burner assembly.

(8.) Clean flame sensor with fine steel wool.
(9.) Reinstall the insulation assembly.

NOTE

: If insulation assembly is damaged, do not attempt to

repair, must be replaced with insulation kit.

NOTE

: Proper use of Personal Protective Equipment (PPE)

must be followed, including safety glasses, gloves, and dust mask

when removing and reinstalling the heat exchanger insulation
assembly.

(10.) Reinstall burner assembly.

10. Remove old sealant from cell panel and collector box

flange.

11. Spray releasing agent on the heat exchanger cell panel

where inducer cover assembly contacts cell panel.

NOTE

: A releasing agent such as cooking spray or equivalent

(must not contain corn or canola oil, aromatic or halogenated
hydrocarbons or inadequate seal may occur) and RTV sealant
(G.E. 162, 6702, or Dow- Corning 738) are needed before
starting installation.

NOTE

: DO NOT substitute any other type of RTV sealant.

12. Apply new sealant to flange of collector box and attach to

cell panel using existing screws, making sure all screws

are secure.

13. Reconnect wires to the following components. (Use

connection diagram on wiring label, if wires were not

marked for reconnection locations.):

a. Burner thermal switch

b. Inducer motor

c. Transducer

d. Limit over- temperature switch

e. Gas valve

f. Hot surface igniter

g. Flame- sensing electrode

14. Reinstall vent connector on furnace vent elbow. Securely

fasten vent connector to vent elbow with two (2)

field- supplied, corrosion- resistant, sheet metal screws

located 180

_

apart.

15. Replace blower access door only, if it was removed.
16. Set thermostat above room temperature and check furnace

for proper operation.

17. Verify blower airflow and speed changes between heating

and cooling.

18. Check for gas leaks.
19. Replace outer access door.

A180229

Fig. 37 - Cleaning Heat Exchanger Cell

FIRE OR EXPLOSION HAZARD

Failure to follow this warning could result in personal injury,

death and/or property damage.
Never purge a gas line into a combustion chamber. Never

test for gas leaks with an open flame. Use a commercially

available soap solution made specifically for the detection of

leaks to check all connections.

!

WARNING

SEQUENCE OF OPERATION
NOTE

: Furnace control must be grounded for proper operation

or control will lock out. Control is grounded through
green/yellow wire routed to gas valve and gas valve mounting
bracket screw.
Follow the sequence of operation through the different modes.

Read and follow the wiring diagram very carefully.
The blower door must be installed for power to be conducted
through the blower door interlock switch ILK to the furnace

control CPU, transformer TRAN, inducer motor IDM, blower
motor BLWM, hot- surface igniter HSI, and gas valve GV.

Summary of Contents for WFEU Series

Page 1: ...4 START UP ADJUSTMENT AND SAFETY CHECK 26 START UP PROCEDURES 26 ADJUSTMENTS 26 CHECK SAFETY CONTROLS 28 SERVICE AND MAINTENANCE PROCEDURES 30 INTRODUCTION 31 ELECTRICAL CONTROLS AND WIRING 31 CARE AN...

Page 2: ...and ventilation air to the furnace space as specified in Air for Combustion and Ventilation section 4 Combustion products must be discharged outdoors Connect this furnace to an approved vent system on...

Page 3: ...FURNACE SIZE A B C D VENT CABINET WIDTH IN MM OUTLET WIDTH IN MM TOP FLUE COLLAR ONLY IN MM BOTTOM WIDTH IN MM VENT CONNECTION SIZE IN MM SHIP WT LB KG WFEU040B036 17 1 2 445 15 7 8 403 11 9 16 294 16...

Page 4: ...ational Fuel Gas Code NFGC NFPA 54 ANSI Z223 1 and the Installation Standards Warm Air Heating and Air Conditioning Systems ANSI NFPA 90B General Installation S Current edition of the NFGC and the NFP...

Page 5: ...Firmly touch the clean unpainted metal surface of the furnace chassis which is close to the control Firmly touch the clean unpainted metal surface of the furnace chassis which is close to the control...

Page 6: ...nstallations may require OUTDOOR AIR for combustion due to chemical exposures S Commercial buildings S Buildings with indoor pools S Laundry rooms S Hobby or craft rooms and S Chemical storage areas I...

Page 7: ...00 4 400 5 500 6 600 0 20 3 150 4 200 5 250 3 300 4 950 6 600 8 250 9 900 0 10 6 300 8 400 10 500 6 600 9 900 13 200 16 500 19 800 0 00 NP NP NP NP NP NP NP NP Air Changes Hour FIRE HAZARD Failure to...

Page 8: ...ON AIR OPENINGS SHALL BE AT LEAST 3 IN 305mm 305mm 305mm 305mm 305mm 76mm Minimum dimensions of 3 in 76 mm NOTE Use any of the following combinations of openings A B C D D E F G A03174 Fig 7 Air for C...

Page 9: ...reely communicates with the outdoors provided there are adequate permanent ventilation openings directly to out doors having free area of at least 1 in 2 4 000 Btuh of total input rating for all gas a...

Page 10: ...ved for use on combustible flooring when any one of the following 3 accessories are used S Downflow combustible floor subbase S Manufacturer s approved Cased Coil or Coil Casing 1 Determine applicatio...

Page 11: ...20 508 20 508 HORIZONTAL INSTALLATION FIRE EXPLOSION AND CARBON MONOXIDE POISONING HAZARD Failure to follow this warning could result in personal injury death and or property damage Do not install th...

Page 12: ...ing the furnace the return air shall also be handled by duct s sealed to the furnace casing and terminating outside the space containing the furnace Secure ductwork with proper fasteners for type of d...

Page 13: ...A02020 Fig 14 Duct Flanges 1 4 6mm THREADED ROD 4 REQ SECURE ANGLE IRON TO BOTTOM OF FURNACE WITH 3 8 x3 4 19mm SCREWS TYPICAL FOR 2 SUPPORTS 1 25mm SQUARE 1 1 4 x1 1 4 x1 8 32x32x3mm ANGLE IRON OR U...

Page 14: ...CH STRAP THE STRAPS SHOULD BE VERTICAL AGAINST THE FURNACE SIDES AND NOT PULL AWAY FROM THE FURNACE SIDES METHOD 1 FOLD ALL STRAPS UNDER FURNACE AND SECURE WTH 4 8 x 3 4 19 mm SHEET METAL SCREWS 2 SCR...

Page 15: ...pipe shall be installed at the furnace gas control valve and extend a minimum of 2 in 51 mm outside the furnace WARNING Gas piping must be installed in accordance with national and local codes Refer t...

Page 16: ...ow performance included 3 4 in 19 mm washable filter media such as contained in factory authorized accessory filter rack To determine airflow performance without this filter assume an additional 0 1 i...

Page 17: ...ge without notice 17 441 01 7201 00 A02075 Fig 19 Upflow Return Air Configurations and Restrictions A02163 Fig 20 Downflow Return Air Configurations and Restrictions A180279 Fig 21 Horizontal Return A...

Page 18: ...n electrical fault should occur This may consist of electrical wire conduit approved for electrical ground or a listed grounded power cord where permitted by local code when installed in accordance wi...

Page 19: ...ound wire to green ground screw on J Box bracket 5 Connect line voltage leads as shown in Fig 24 6 Reinstall cover to J Box Do not pinch wires between cover and bracket BX CABLE INSTALLATION IN FURNAC...

Page 20: ...C LINE CONNECTION L1 INDUCER MOTOR AND IGNITER 115 VAC NEUTRAL CONNECTOR ECM BLOWER 115VAC PRIMARY OF TRANSFORMER 115 VAC EAC 115 VAC WHEN USED FLAME SENSOR HUMIDIFIER 115 VAC WHEN USED NO CONNECTION...

Page 21: ...uilding codes the current edition of National Fuel Gas Code ANSI Z223 1 NFPA 54 NFGC Parts 12 and 13 the local building codes and furnace and vent manufacturers instructions These furnaces are design...

Page 22: ...207 299 15 4 5 NR 152 233 334 20 6 0 NR NR 250 368 30 9 1 NR NR NR 404 Table 9 Minimum Allowable Input Rating of Space Heating Appliance in Thousands of BTUH per Hour VENT HEIGHT FT M INTERNAL AREA O...

Page 23: ...Specifications are subject to change without notice 23 441 01 7201 00 A180242 Fig 25 Chimney Inspection Chart...

Page 24: ...ow does NOT count as part of the number of vent connector elbows The vent connector can exit the furnace through one of two locations on the casing 1 Attach the single wall vent connector to the furna...

Page 25: ...TES 1 2 4 7 8 9 on the page following these figures A03213 Fig 28 Horizontal Left Application Vent Elbow Left SEE NOTES 1 2 4 5 6 7 8 9 on the page following these figures A03207 Fig 29 Downflow Appli...

Page 26: ...Failure to make proper con nections will result in improper operation See Fig 24 3 Gas supply pressure to the furnace must be greater than 4 5 In W C 0 16 psig but not exceed 14 In W C 0 5 psig 4 Chec...

Page 27: ...liances and pilots served by the meter b Run furnace for 3 minutes in heating operation c Measure time in seconds for gas meter to complete 1 revolution and note reading The 2 or 5 cubic feet dial pro...

Page 28: ...cord amp draw across terminals when furnace is in heating and after blower starts 4 Set heat anticipator on thermostat per thermostat in structions and install on subbase or wall R Y W G 10 TURNS THER...

Page 29: ...kage from furnace vent elbow g Switch will auto reset when it cools h Re install vent connector Table 10 Gas Rate Cu Ft Hr SECONDS FOR 1 REVOLUTION SIZE OF TEST DIAL SECONDS FOR 1 REVOLUTION SIZE OF T...

Page 30: ...tlet Pressure for Gas Heat Values at Altitude 100 000 Tabulated Data Based on 100 000 BTUH Input for 0 ft 0m to 2000 ft 1524 M above sea level ALTITUDE RANGE ft m RANGE ft m HEAT VALUE AT ALTI TUDE Bt...

Page 31: ...trol See Fig 38 Any shorts of the 24 v wiring during installation service or maintenance will cause this fuse to blow If fuse replacement is required use ONLY a 3 amp fuse The control LED will display...

Page 32: ...essary 4 Check electrical connections for tightness and controls for proper operation each heating season Service as necessary 5 Inspect the vent pipe vent system before each heating season for rust c...

Page 33: ...6 If furnace is operating properly RELEASE BLOWER ACCESS DOOR SWITCH Remove any jumpers or reconnect any disconnected thermostat leads Replace blower access door 17 Reinstall outer door 18 Cycle furna...

Page 34: ...equate seal may occur and RTV sealant G E 162 6702 or Dow Corning 738 are needed before starting installation NOTE DO NOT substitute any other type of RTV sealant 12 Apply new sealant to flange of col...

Page 35: ...ation of the Heat Blower Off Delay timing The Heat Blower Off Delay is field selectable 90 120 150 180 NOTE 120 is default setting OFF The controls returns to the stand by mode until either a thermost...

Page 36: ...Specifications are subject to change without notice 36 441 01 7201 00 A180211 Fig 38 Wiring Diagram...

Page 37: ...ses and the CFH is present the furnace returns to normal operation Check Main limit Draft Safeguard Burner Thermal Switch are all in the Main Limit Circuit Check for any blockages in flue pipe or blow...

Page 38: ...IZE MAJOR SERIES MINOR SERIES WFEU 060 C 60 A 1 TO OBTAIN INFORMATION ON PARTS Consult your installing dealer or the classified section of your local telephone directory under the Heating Equipment or...