INSTALLATION SEQUENCE:

• 1-2: THE BATHTUB IS LEVELED VIA A WATER LEVEL AT THE INTENDED LOCAL INSTALLATION AREA.
• 3: PLACE THE BATHTUB BY RAISING IT UP 30” WITH 4X4 PEICES OF LUMBER SO YOU CAN HAVE ACCESS FROM THE BOTTOM OF THE BATHTUB. 

IMPORTANT NOTE: DURING THE INSTALLATION, THE BATHTUB SHOULD NOT BE TURNED ON ITS SIDE TO PREVENT ITS WEIGHT FROM DEFLECTING ITS 
MONOBLOC SIDES.  THIS IS WHY IT IS IMPORTANT TO USE SUPPORTS TO RAISE THE BATHTUB ABOVE THE FLOOR.

  THIS WILL ALSO PROVIDE YOU WITH EASY ACCESS TO THE INTERNAL PLUMBING PARTS.

• 4: THE MONOBLOC SIDES OF THE BATHTUB TOUCHING THE FLOOR SHOULD BE MARKED.
• 5: THE WATER OUTLET PIPE SHOULD BE CONNECTED.
• 6: FOOT LEVELING LOCK NUTS ARE ADJUSTED.

• 7: SILICONE IS APPLIED TO THE FEET OF THE BATHTUB THAT STANDS ON THE FLOOR.
• 8: WHEN THE INSTALLATION IS COMPLETED, THE BATHTUB IS TAKEN DOWN FROMN THE SUPPORTS ( IE 2 X 4X4'S).
  IF NECESSARY, INSTALLATION IS COMPLETD BY APPLYING SILICONE AT SEVERAL POINTS BETWEEN THE BOTTOM PANEL AND FLOOR.
• 9: ANY REMAINING PROTECTIVE PACKAGING SHOULD BE REMOVED ONLY AFTER THE BATHTUB INSTALLATION AND OTHER
  CONSTRUCTION WORK IN THE BATHROOM IS FULLY FINISHED.