SULFURYL FLUORIDE MANUAL REV C
PAGE 10 OF 23
04/07/11
CALIBRATION
Note:
Should be done every 3 months or more frequent. Some companies
require
monthly calibration.
The instrument is calibrated by introducing, a known concentration of Sulfuryl
Fluoride gas (5 ppm), and adjusting the SPAN control to correspond to the known
analysis of the gas.
NOTE
: New or replacement sensors may require approximately 24 hours to stabilize prior to
zeroing.
With the unit turned on and sufficiently warmed up with the
READY
light
illuminated, zero the analyzer with the
ZERO
control. Fill a sample bag with Sulfuryl
Fluoride standard, and connect it to the inlet, allowing the gas to flow for at least 3
minutes.
DO NOT ATTEMPT TO INTRODUCE THE VIKANE
STANDARD DIRECTLY FROM A PRESSURIZED SOURCE. A
SAMPLE BAG MUST BE USED.
Do not introduce concentrations higher than 50 ppm.
The
CAL
control is used to set the meter to a value corresponding to the span
gas concentration. Disconnect the sample bag. Allow to stabilize for 3 minutes.
Repeat procedure two additional times.
The readings should be within
±
2 divisions of the average of your three readings.
Summary of Contents for GF1900
Page 1: ...SULFURYL FLUORIDE MANUAL REV C PAGE 1 OF 23 04 07 11 GF 1900 SULFURYL FLUORIDE ANALYZER ...
Page 2: ...SULFURYL FLUORIDE MANUAL REV C PAGE 2 OF 23 04 07 11 ...
Page 15: ...SULFURYL FLUORIDE MANUAL REV C PAGE 15 OF 23 04 07 11 Figure 3 BC1 24V PATTERY PACK CHARGER ...
Page 17: ...SULFURYL FLUORIDE MANUAL REV C PAGE 17 OF 23 04 07 11 DIAGRAMS SCHEMATICS PARTS ...
Page 18: ...SULFURYL FLUORIDE MANUAL REV C PAGE 18 OF 23 04 07 11 ...
Page 19: ...SULFURYL FLUORIDE MANUAL REV C PAGE 19 OF 23 04 07 11 ...
Page 22: ...SULFURYL FLUORIDE MANUAL REV C PAGE 22 OF 23 04 07 11 ...