21
INSTALLATION AND ASSEMBLY
aV100 extract air system – Avio N 100
•
Installation and operating instructions
5.2
Creating a plaster slot/wall opening for the wall sleeve
DANGER
Ingress of water into aV100 extract air system
Electric shock and/or overheating due to short circuit (230V, 50Hz)!
►
Create wall opening for aV100 extract air system outside protection area 0.
CAUTION
Falling masonry when creating the wall opening.
Injury to persons and/or damage to property!
►
Install protection against falling masonry on building exterior.
►
Remove objects from the immediate vicinity of the building's exterior.
TIP
Creating the wall opening for the wall sleeve is shown below when mounting the extractor fan
into the wall sleeve on the exterior wall.
When mounting the extractor fan subceiling the wall opening for the wall sleeve must be created
on the exterior wall between ceiling and subceiling.
Additionaly on the subceiling a 105 mm diameter hole for the fan must be cut. The power cable
must be laid (only when mounting subceiling!) between ceiling and subceiling to the hole for the
fan instead of the wall sleeve. The connection between wall sleeve and extractor fan must be
carried out on site.