21
INSTALLATION AND ASSEMBLY
21
iV-Smart+ ventilation device | Installation instructions
4.3 Laying the cables to the wall opening of the ventilation device
DANGER
Exposed electrical components.
Electric shock and injury due to live components (230 V, 50 Hz)!
•
Installation and connection must only be performed by qualified and trained personnel.
Cable to the wall opening of the ventilation device
The following cables, depending on the control device, are laid to the wall opening for the ventila-
tion device:
Use
Cable type
Cable origin
Pure
Operating voltage fan
and
device communication
Stranded cable
6 – 16 V DC,
e. g.: LiYY 3x0.75 mm²
Pure control module
sMove
sMove operating device
MZ-Home
Clust-Air module CAM17
in the ventilation zone
inVENTer
Connect
(Connect inner cover)
Connect inner cover
operating voltage
Installation cable
230 V AC,
e. g.: NYM-J 3x1.5 mm²
House distribution,
ventilation
sub-distribution
Unit communication
(only if the system compo-
nents communicate by cable
[otherwise radio])
RS485 data cable,
e. g.:
Type J-Y(ST)Y 2x2x0.8 mm²
Easy Connect e16
operating device
Once the wall opening has been created, the cables necessary for operating the ventilation
system are laid to the wall opening for the ventilation device. They connect the valve gate of the
ventilation device with the control components and thus establish signal transmission and/or
voltage transmission between the controller and the Xenion reversible fan.
NOTICE: Cable to the wall opening of the ventilation device not
laid.
No connection of the reversible fan possible!
Routing of the cables to the wall opening for the ventilation device
must be done in this installation step. The routing of the connection
cables to the Connect inner cover or between the controllers and
the Xenion reversible fan is not part of this documentation. For
more information, see the installation instructions for the corre-
sponding controller.
45°