INSTALLATION GUIDELINES

STEP 1 

Refer to PLAN VIEW and FOOTING LAYOUT to locate position of swing frame.

Detail A

Top Bar

STEP 2

Excavate footing as shown in FOOTING LAYOUT and FOOTING DETAIL. Place a 2” spacer block in 

the bottom of each hole.

STEP 3

Select two arched swing frame ends, three top bars, two swing frame middle sections and twelve set 

screws. Set swing frame ends and middles into place in footing holes and brace into position. Slide one 

top bar over swing frame end and middle stubs and hold top bar in place with pre-drilled holes and nuts 

at the 6:00 position. Secure each end of top bar using two set screws. Repeat for each top bar (see Detail 

A and B).

STEP 4

Verify that swing frame is level and plumb in footings and that it is at correct height. 

NOTE:

  Center of top 

bar needs to be 96” above finished surfacing. Pour concrete in footings to correct level. 

NOTE:

  Concrete 

must have a minimum rating of 2,500 psi and must be mixed per manufacturer’s recommendations. Fill 

remainder of hole with dirt. Allow concrete to harden  for at least 48 hours before use! For safety reasons, 

do not attach swing chains or seats to swing frame until playground is ready to open. 

NOTE: 

 Swing seats 

and chains sold separately.