DIAGONAL BRACeS (OPTIONAL)
GROUND MOUNT INSTALLATION MANUAL - 13
© 2019 IRONRIDGE, INC. VERSION 2.8
Use IronRidge's Microinverter Kit to bond compatible microstroage
devices to the racking system. Insert Microinverter Kit T-bolt into top
rail slot. Place compatible microstorage into position and tighten hex
nut to
80 in-lbs
.
Microinverter Kit
(80 in-lbs)
SYSTeMS USING MICROSTORAGe PRODUCTS
Insert Frameless Kit T-bolt in top rail slot. Place star
washer over T-bolt, allowing it to rest on top of rail. Secure
module clamps with a hex nut and torque to
80 in-lbs
.
Place
Star Washer
Module Clamp
(80 in-lbs)
Grounding Lugs
Required on Every Rail
FRAMeLeSS MODULe KITS
COMPATIBLe PRODUCTS
PHAZR
PHAZR Devices PHAZR-X, where X is 6-12.
➢
Running a separate equipment grounding conductor to the PHAZRs is
not required.
➢
If installing in areas with ground snow loads greater than 40 psf and
underneath a module, install PHAZR devices as close as possible to
module frame edge.
➢
Use the number of IronRidge Microinverter kits allowed by the
microstorage mounting flange. Some will require 1 kit and others 2 kits.
COMPATIBLe PRODUCTS
Sunforson
Sunforson silver or black SFS-UTMC-200(B) mid and SFS-UTeC-
200(B) end clamps.
Sunpreme
Sunpreme silver or black mid and end clamps with part numbers
7500105X where “X” is 1, 5, 6 or 7.
Ironridge
IronRidge silver or black mid and end clamps with part numbers
FMLS-XC-001-Y where “X” is E or M and “Y” is B or blank.
➢
Follow module manufacturer’s installation instructions to install
the module clamps.
➢
Frameless modules require using a Grounding Lug on every
rail.
➢
For Sunpreme Modules Only: If required to use slide prevention
hardware, see Module Slide Prevention Addendum (Version
1.10).