| Standard Rail Installation Manual
2.
Complete the clamp assembly
with a flange nut as shown.
Tighten to 60-65 in-lbs.
3.
Repeat with the other clamp.
4.
Working from the opposite side
of the PV module. Assemble
the center clamps by putting a
clamp on the bolt, followed by
the flange nut.
5.
Place the second PV Module
into position on the rails, sliding
it against the first so the center
clamps are in contact with the
edges of both panels.
(Note- For
installations that utilize WEEBs,
please refer to Wiley/Burndy in-
stallation manual for “IronRidge
Light and Standard Series Rails”
for proper installation proce-
dures.)