5.3 Commissioning
Envistar Top (code TEM, TXM, TER, TXR) and Envistar Top with integrated Eco-
Cooler (code TEC) cooling unit or reversible heat pump ThermoCooler HP (code
TTC) are factory built units that are tested and documented in the factory.
Commissioning of the unit must be carried out by competent personnel in ac-
cordance with the Commissioning Procedure:
• For Envistar Top, refer to
Commissioning Checklist for air handling units
at
• For Envistar Top with integrated cooling unit, refer to
Envistar Top with EcoCooler, Commissioning record
at
• For Envistar Top with integrated reversible heat pump, refer to
Envistar Top with ThermoCooler HP, Commissioning record
at
The commissioning procedure applies to units that are supplied with control
equipment (code MX).
The validity of the product warranty is conditional on the system having been
correctly commissioned. Working on the cooling unit during the warranty period
without the approval of IV Produkt shall render the warranty void.
Prior to commissioning, the contractor must:
NB:
Wiring of connections and other electrical work may only be carried out
by a qualified electrician or by service personnel recommended by IV
Produkt.
1. Connect the unit to the power supply via a lockable safety switch.
2. Connect the heating/cooling coil, if relevant.
3. Connect the electrical quick-connectors between the unit parts in a modular
design.
4. Installation of the pressure sensor and its hoses.
5. Installation and wiring temperature sensor.
5. Connect all ducts.
WARNING!
Rotating fan impeller. The unit must not be energised until all
ducts have been connected.
Follow the troubleshooting instructions in the troubleshooting chart before
contacting a service representative for servicing a unit under warranty. This will