Technology Description-

 Floating, electric powered, circulation and Trihalomethane (THM) removal equipment for po-

table water tanks and reservoirs. Designed for continuous operation and factory installed through 24-inch diameter, clear 
and unobstructed hatch opening.

Figure 1:

 SN10

Electrical Requirements - 

 Requires 240VAC/3PH or 480VAC/3PH, 60Hz power. Ixom recommends secondary

disconnect to be located near equipment access hatch. Optional Franklin SubMonitor three-phase motor protection unit 
highly recommended and available from Ixom. 

All switches, breakers, emergency stop buttons, control panels and other 

controls shall be installed in accordance to all NEC, State, and local regulations. 

(Not supplied by Ixom)

Patent Pending 

Subject to change without notice.

Certifications

 - Ixom's potable water products are certified to ANSI/NSF Standard 61, and 372 for lead-free content. 

Learn more at:  www.medoraco.com/std61

Maintenance / Warranty 

- Limited maintenance.  Limited 2-year parts and labor warranty.  See Warranty Statement for 

details.

Spray Unit Direct Flow Rate

 - 0.90 million gallons per day, 

MGD. 

Ixom application engineering evaluations often require 

sizing systems based on site specific conditions and NOT 

the spray aeration direct flow rate.

Minimum Water Depth

 - Minimum of 5ft (1.5m) operating 

depth required, 

do not operate out of water.  Minimum of 

6.25ft (1.9m) depth required with leg extensions.

Minimum Head Space

 - Minimum of 30in (76cm) head 

space between water level and reservoir/tank ceiling 
required. 

(Contact Ixom for exceptions that can be 

made.)

Sealed Penetration Fitting - 

T316 stainless steel tank fitting with a 3/4” NPT female connection.  Not designed 

as a submersible penetration.

Wiring -

 4-conductor, submersible power cable for submersible motor wiring terminated exterior at top of tank.

Motor -

 10HP stainless steel submersible, designed for continuous operation, low power requirement, direct drive, 

no gearbox and no lubrication schedule required. See certifications section below.

Materials of Construction

 - T316 stainless steel,

thermoplastic rubber, high density polyethylene construction. 
GridBee

®

 machines are constructed using safe materials for 

contact with potable water.   See certifications section below.

TTHM Reduction Range

 - 20% to 70%, dependant on 

THM species, daily inflow and other variables, see Ixom for 

proposal.

Minimum Access Opening

 - Machine can be placed 

through  24-inch (61cm) diameter, clear and unobstructed 

hatch opening.  

Intake -

 20 to 100+ feet (6 to 30+ m) available in 12-inch (30.5 cm) diameter X 20 feet (6 m) sections, thermoplastic

rubber, NSF/ANSI 61 approved. Includes low elevation intake that draws water in a horizontal layer within 18 inches

(45 cm) of the tank or reservoir floor. Includes intake retrieval chain constructed of 316 stainless steel.

Shipping Size / Weight

  •  Crate -

 72in x 48in x 59in (1.85m x 1.22m x 1.5m) / 1200lbs (550kg) 

Exact weight and dimensions varies dependent 

on machine configuration.

132”

36”

30”

75”

© 2020 Ixom | www.medoraco.com | 866 - 437 - 8076 | info@medoraco.com

Technical Data Sheet

SN10

1554_10016_20201006

O&M_SN10_10030_10104_20201006 - 10

Summary of Contents for Medora GridBee SN10

Page 1: ...2020 Ixom www medoraco com 866 437 8076 info medoraco com O M_SN10_10030_10104_20201006 GridBee SN10 Owner s Manual...

Page 2: ...astewater Treatment Processes Ixom equipment continues to be at the forefront as the 1 world leader for in situ water body treatment 2020 Ixom www medoraco com 866 437 8076 info medoraco com Table of...

Page 3: ...t You can avoid hazards by following these safety instructions and applying some ordinary common sense when operating or servicing this unit Keep in mind that full operator attention and alertness are...

Page 4: ...ative ELECTRICAL HAZARD WARNING THIS EQUIPMENT CONTAINS HIGH VOLTAGE ELECTRICAL SHOCK CAN CAUSE SERIOUS OR FATAL INJURY ONLY QUALIFIED PERSONNEL SHOULD ATTEMPT PLACEMENT OPERATION AND MAINTENANCE OF E...

Page 5: ...with all relative OSHA and local regulations while installing and performing any maintenance to the mixer circulation equipment Key OSHA Compliance Standards that must be followed and not limited to...

Page 6: ...Tethered with dual tether system Electrical Control Panel located at bottom of tank Blower placed over top of machine Blower size depends on tank specifics and application Blower shown as roof mount c...

Page 7: ...DETAIL 4 Diameter Chain Loop 316 Stainless Steel Chain Approx 6 MOORING CONNECTION DETAIL 2020 Ixom www medoraco com 866 437 8076 info medoraco com SN Machine Dual Tethering Visual Dual Tethering SN...

Page 8: ...00 28 9 15800 77 95 81 81 161 H 460 60 1 15 20 8 13700 23 7 15800 1 1 1 4 81 81 133 H TYPE RATING CIRCUIT BREAKERS OR FUSE AMPS CIRCUIT BREAKERS OR FUSE AMPS MAXIMUM PER NEC TYPICAL SUBMERSIBLE HP KW...

Page 9: ...AL HDPE STRAIN RELIEF WASHER BRASS NUT 316SS UNIVERSAL FIXTURE 3 4 NPT FEMALE THREADS FOR CONDUIT CONNECTION POINT BRASS NUT T316SS 3 4 MNPT GLAND SEAL 316SS QUICK LINK MESH STRAIN RELIEF INSIDE TANK...

Page 10: ...while unit is running L1 2 L1 2 L2 L3 L1 L3 Amperage Reading while unit is running Reference Wiring Full Load Max Load L1 L1 L2 L3 Flow Check Auditory Flow Check Visual Final Checks Now that the insta...

Page 11: ...n severely worn coupling between pump and motor pump and or motor replacement Motor Amperage is high Low Unbalanced line voltage check source power Phase loss check source power Short to ground check...

Page 12: ...ead space between water level and reservoir tank ceiling required Contact Ixom for exceptions that can be made Sealed Penetration Fitting T316 stainless steel tank fitting with a 3 4 NPT female connec...

Page 13: ...PN 100541 Platform Assembly 7 PN 100284 Collapsible Float 8 PN 100395 Float Arm 9 PN 26061220 NSF Hose 12 x 20 10 PN 16013107 Hose Clamp 12 2 6 Clamps 11 PN 101464 Intake Assembly 08 01 06 10 09 07 0...

Page 14: ...6 Collapsed 30 Min Head Space 75 Min Operating Depth 2020 Ixom www medoraco com 866 437 8076 info medoraco com Dimension Drawing SN10 Dimension Drawing 1551_10033_20201006 O M_SN10_10030_10104_2020100...

Page 15: ...ts There is no liability for consequential damages of any type The warranty that is submitted and provided with the purchased equipment is the valid warranty GridBee control panels and any optional ac...

Page 16: ...and other related subjects as required by OSHA to perform the necessary work to install or remove SolarBee and GridBee equipment and are knowlegeable in the regulations and standards of OSHA If you fe...

Reviews: